6  Connection
1. Connect the connection cable to the analogue signal source (see the manufacturer manual). For
this purpose, trim the unused insulated wires up to the cable shield and note the wire colours.
2. Connect the connection cable to the eight-pole plug as follows:
• Release conductor entry 8 using a screwdriver and insert the insulated wire of the single core
into the conductor entry.
• Release conductor entries 6 and 7 using a screwdriver and insert the insulated wires of the
connection cable into the conductor entries. Observe the pin assignment.
3. Insert the eight-pole plug at terminal X8 into pin row A.
4. On the connection cable, mark the terminal and pin row to which the connection cable is
assigned. For this purpose, use the cable ties with the caption field.
5. On the supplementary sheet for noting the connected devices, note the terminal to which the
analogue signal source is assigned.
50
ClusterController-IA-en-10
SMA Solar Technology AG
Installation Manual

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the CLUSTER CONTROLLER and is the answer not in the manual?

Questions and answers

Table of Contents