Completing the Installation
Fixing the Outdoor Unit in Place
Unit : inch(mm)
26(660)
Rubber leg
Final Checks and Trial Operation
14
E-
Page 14
You should install the outdoor unit on a stable base to avoid the generation of
noise and vibration, especially when installing the outdoor unit close to your
neighbor.
If you install the outdoor unit in a place exposed to strong winds or at a height,
you must fix it to the appropriate support (wall or ground).
1
Place the outdoor unit as indicated on the top of the unit to let the discharged air out
properly.
2
Fix the outdoor unit to the appropriate support using anchor bolts.
3
If the outdoor unit is exposed to strong winds, install shield plates around
the outdoor unit, so that the fan can operate correctly.
➢
Secure the rubber leg in order to prevent the generation of noise and
vibration.
To complete the installation, perform the following checks and tests to ensure
that the air conditioner operates correctly.
1
Check the following.
N Strength of the installation site
N Tightness of pipe connection to detect a gas leak
N Electric wiring connection
N Heat-resistant insulation of the pipe
N Drainage
N Earth conductor connection
N Correct operation (follow the steps below)
2
Press the
button for 5 seconds. Or press the K1 switch of the display board
twice(Cooling test operation) or 3 times(Heating test operation) after removing the side
cover of the outdoor unit.
N The LED of the indoor unit displays the option code.
N The airflow blade swings up and down and the indoor fan operates.