Safety Test Requirements - Philips TFT LCD Colour Monitor Service Manual

19” tft lcd colour monitor
Table of Contents

Advertisement

27
190B4 LCD
All units that are returned for service or repair must pass the
original manufactures safety tests. Safety testing requires both
Hi-pot and Ground Continuity testing.
HI-POT TEST INSTRUCTION
1. Application requirements
1.1 All mains operated products must pass the H-Pot test as
described in this instruction.
1.2 This test must be performed again after the covers have
been refitted following the repair, inspection or modification
of the product.
2. Test method
2.1 Connecting conditions
2.1.1 The test specified must be applied between the
parallel-blade plug of the mainscord and all accessible
metal parts of the product.
2.1.2 Before carrying out the test, reliable conductive
connections must be ensured and thereafter be
maintained throughout the test period.
2.1.3 The mains switch(es) must be in the "ON" position.
2.2 Test Requirements
All products should be Hi-Pot and Ground Continuity tested as
follows¡ G
Condition
Hi-Pot Test for
products
where the
mains input
range is Full
range (or
220VAC)
Test voltage
2820VDC
(2000VAC)
Test time
3 seconds
(min.)
Trip current
Set at 100uA
(Tester)
for Max.
limitation; set
at 0.1uA for
Min. limitation
Ramp time
Set at 2
seconds
2.2.1 The test with AC voltage is only for production purpose,
Service center shall use DC voltage.
2.2.2 The minimum test duration for Quality Control Inspector
must be 1 minute. No breakdown during the test.
2.2.3 The test voltage must be maintained within the specified
voltage + 5%.
2.3.4 The grounding blade or pin of mains plug must be
conducted with accessible metal parts.

Safety Test Requirements

Hi-Pot test
Ground
for products
Continuity test
where the
requirement
mains input
is 110VAC
(USA type)
1700VDC
Test current:
(1200VAC)
25A, AC
1 second
Test time:
3 seconds(min.)
Resistance
5mA
required:
¡ Ø 0.09+R ohm,
R is the
resistance of
the mains cord.
3. Equipments and Connection
3.1 Equipments
For example¡ G
- ChenHwa 9032 PROGRAMMABLE AUTO SAFETY
TESTER
- ChenHwa 510B Digital Grounding Continuity tester
- Chen Hwa 901 (AC Hi-pot test), 902 (AC, DC Hi-pot test)
Withstanding tester
3.2 Connection
* Turn on the power switch of monitor before Hi-pot and
Ground Continuity testing.
4. Recording
Hi-pot and Ground Continuity testing records have to be kept
for a period of 10 years.