Pre-Commissioning Checks - Worcester GREENSTAR 24i junior Instruction Manual

Wall hung rsf gas fired condensing combination boiler, for sealed central heating systems and mains fed domestic hot water
Table of Contents

Advertisement

1
A
A
D
C
22mm
15mm
22mm
15mm
2
F
INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER GREENSTAR 24 i junior/28 i junior
8 716 115 166b (03/2009)
D
E
C
E
B
22mm
Condensate pipe
PRE-COMMISSIONING
CHECKS
B
CAUTION: ISOLATE THE MAINS
SUPPLIES BEFORE STARTING ANY
WORK AND OBSERVE ALL
RELEVANT SAFETY PRECAUTIONS
1 Check that the service and water pipes are
connected to the correct position on the
manifold.
A - CH Flow (22mm)
B - CH Return (22mm)
C - Gas inlet (22mm)
D - DHW (15mm)
E - Water in (15mm)
2 Check the gas type specified on the
identification plate (F) matches that of the
gas supply. Turn on the main gas supply,
check the gas pipework, connections and
rectify any leaks.
3 Check that the condensate pipe has been
connected to the syphon.
4 Check pressure relief drain pipe (J) is
J
correctly fitted and securely tightened.
IMPORTANT: If the boiler is not to be
commissioned immediately then:
after successfully completing all of the
checks and any rectification work,
close the gas and water valves, shut off
the gas supply and electrically isolate
the boiler and label appropriately.
3
3
Preplumbing manifold
connector

PRE-COMMISSIONING CHECKS

J
31

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Greenstar 28i junior

Table of Contents