Basic Frame; Single Station; In-Line Station; Alignment - LISTAESCAN ARLINK 8000 Instructions For Assembly

Table of Contents

Advertisement

Install all leveling glides before starting assembly. The column glide should only be threaded half way into
the column, while the outrigger glides should be threaded into the outriggers their full length.
Install outriggers by inserting the tongues of the outrigger into the center slot or Macro slot of the column.
Secure with clevis pins through the tongues of the outrigger, then insert the retainer through the hole in the
clevis pin. Outriggers must be positioned as shown below to ensure correct alignment of the in-line system
as well as correct alignment for footrest mounting.
Single Station Assembly
Stabilizer panels are mounted between the columns
with "T" bolts. Usually these are mounted through
the second, fourth, and ninth holes from the bottom
of the columns.
The access slot in the stabilizer channel should be
positioned over the third hole from the bottom of the
column to provide access to the outrigger clevis pin
and retainer.
Mount the stabilizer using the 1/4-20 x 2" "T" bolts,
1/4" washers, and 1/4-20 wing nuts provided.
Basic Frame Assembly
Begin by assembling all columns and outriggers.
Then assemble the first column and stabilizer in the
manner described previously. The middle column
will have two stabilizers mounted to it. Therefore you
must bolt through the column and both stabilizers.
This procedure is repeated for each successive
workstation. At the last column of your in-line
station ensure the "T" bolt is facing the stabilizer
panel.
Alignment of the system is necessary at this point.
The columns must be both vertically and horizontally
aligned. This can be accomplished by using a level,
and adjusting the glides. Floor glides must be
adjusted so that each column supports equal weight.
NOTE: Alignment should be re-checked after
accessories are installed.
In-line Assembly

Alignment

Advertisement

Table of Contents
loading

Table of Contents