Single Ups Commissioning; Check Before Power-On; Single Ups Parameters Setting - Liebert NXC User Manual

10/15/20kva
Table of Contents

Advertisement

Liebert NXC

2.5 Single UPS Commissioning

2.5.1 Check Before Power-On

1. Check and confirm that the power distribution mode of the UPS is correct, that the connections of the power cable and signal
cable are correct and there is no short circuit.
2. When used an external Battery, check that the battery installation and the cable connection are correct, positive pole and
negative pole of the battery is correct.
3. Measure and confirm that the mains voltage and frequency are normal.
4. The output terminals of the UPS are energized upon the power-on. If the load is connected with the output terminals, make
sure that the power to the load is safe.

2.5.2 Single UPS Parameters Setting

Power on the UPS according to step 1 ~ step 4 in 2.5.3, it is prohibited to start the inverter.
Press the menu key to enter the function setting option, set the single UPS parameters according to Table 2-5.
Parameters
Single Group Batt Cap
Battery Cells Number
Equalize Charge Allowed
System Configuration
ECO Mode
Output frencency level
Output voltage level
3 Phase Output or 1 Phase
Output
Note: output frequency level and output voltage level will be active after power-off, but will not be displayed on LCD panel, the settings will be
valid after manual power-off.
The parameter descriptions and default values of the other parameters are listed in Table 2-6; you can set the parameters
according to the actual requirements.
User Manual 10H52188UM51 - Rev. 1 - 09/2011
Table 2-5 Single UPS parameters setting
Default value
0014
Set the parameter according to the actual battery capicitity
32
Set the parameter according to the actual battery number
Enabled
Set the parameter according to the actual battery charicteristic
Single
Single
Normal
Normal
50Hz
Set the parameter according to the actual power grid, 50Hz/60Hz can be selected
400V
Set the parameter according to the actual power grid, 380V/400V/415V can be selected
Three
Select "Three" when is 3 Phase Output, select "Single" when is 1 Phase Output
Single UPS Installation and Commissioning
Parameters setting
23

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Nxc li6010 seriesNxc li6015 seriesNxc li6020 series

Table of Contents