Connect the Logger as follows.
The 1745 Logger is prepared for logging in Delta, Delta 2 Element,
Wye (Star), single and split phase. Please note the different types of
connection and configuration in the PQ Log software.
1. Connect all required measuring leads.
2. If you want to supply the Logger from an outlet use the supplied
power cord and plug adapter. The power supply leads can also be
connected in parallel to the voltage test leads, but the voltage is
limited to 660 V RMS AC.
3. Connect the current clamp set or Flexi Set to the Logger.
4. Connect the current sensor to the conductor under test.
5. Connect the dolphin clips to the test leads. For 3-phase, 4-wire
systems, connect the N-test lead first, and then the other phases.