Commissioning; Initial Preparation - Ariston microGENUS HE 24 MFFI Installation And Servicing Instructions

Type c boilers
Hide thumbs Also See for microGENUS HE 24 MFFI:
Table of Contents

Advertisement

3.

COMMISSIONING

3.1
I
P
NITIAL
REPARATION
MTS (GB) Limited support the
Sections 11 and 12 of this manual you will find the
commissioning checklist (page 68) and the
service interval record (Page 69), It is important that the
commissioning checklist is completed in the
presence of your customer, they are shown how to use it,
and it is signed by them. Please instruct your customer
that they must have this manual with them whenever they
contact a service engineer or us.
Carry out preliminary electrical system checks to ensure
electrical safety, this must be carried out by a competent
person i.e. polarity, earth continuity, resistance to earth
and short circuit.
F
H
S
ILLING THE
EATING
YSTEM
Lower the control panel and remove the case panels
(see S
2.12 for further information).
ECTION
Open the central heating flow and retur n cocks
supplied with the connection kit.
Unscrew the cap on the automatic air release valve one
full turn and leave open permanently.
Close all air release valves on the central heating
system.
Gradually open valve(s) at the filling point (filling-loop)
connection to the central heating system until water is
heard to flow, do not open fully.
Open each air release tap starting with the lowest point
and close them only when clear water, free of air, is
visible.
Purge the air from the pump by unscrewing the
pump plug anticlockwise, also manually rotate the
pump shaft in the direction indicated by the pump
label to ensure the pump is free.
Refit the pump plug.
Continue filling the system until at least 1.5 bar
registers on the pressure gauge..
Inspect the system for water soundness and remedy
any leaks discovered.
F
D.H.W. S
ILLING OF THE
YSTEM
Close all hot water draw-off taps.
Open the cold water inlet cock supplied with the
connection kit.
Open slowly each draw-off tap and close them only
when clear water, free of bubbles, is visible.
G
S
:
AS
UPPLY
Inspect the entire installation including the gas meter,
test for tightness and purge the supply as described in
BS 6891:1998.
Open the gas cock (supplied with the connection kit) to
the appliance and check the gas connections on the
appliance for leaks.
W
T
ATER
REATMENT
The detailed recommendations for water treatment are
given in BS 7593:1992 (Treatment of water in domestic
hot water central heating systems); the following notes
are given for general guidance:
initiative. In
:
: