overview Advice for the installer CE labelling The installation and fi rst ignition of the boiler must be The CE mark guarantees that the appliance conforms to the performed by qualifi ed personnel in compliance with following directives: current national regulations regarding installation, and - 2009/142/CE relating to gas appliances in conformity with any requirements established by - 2004/108/CEE relating to electromagnetic compatibility...
overview Safety regulations Handle the appliance with suitable protection and with care. Damage to the appliance or surrounding objects from shocks, knocks, incisions and squashing. Key to symbols: During all work procedures, wear individual protective clothing and Failure to comply with this warning implies the risk of equipment.
product description GENUS PREMIUM EVO HP 115/150 Legend: Combustion analysis test point Flue thermostat Flame inspection glass Ignition electrode Ignitor Modulating fan Minimum water pressure switch Siphon Circulation pump with air release valve 10. Mixer 11. Silencer 12. Gas valve 13.
Overall Dimensions GENUS PREMIUM EVO HP 45/65 Ø 126 Ø 80,5 A. Central Heating Flow 1” M C. Gas Inlet ¾” M E. Central Heating Return 1” M A-C-E-F F. Condesate discharge GENUS PREMIUM EVO HP 85/100 A. Central Heating Flow 1” ¼ M C.
product description GENUS PREMIUM EVO HP 115/150 A. Central Heating Flow 1” 1/2 M A - C - E - F C. Gas Inlet 1” M E. Central Heating Return 1” 1/2 M...
Genus Premium EVO HP is designed to work individually or in cascade (max 8 devices). GENUS PREMIUM EVO HP 45/65 Is necessary that all requirements are met by the rules and regulations for equipment equivalent to the total installed power generators.
View of the Boiler Connections COUNTRY MODEL CATEGORIES GENUS PREMIUM EVO HP 45 GENUS PREMIUM EVO HP 65 GENUS PREMIUM EVOHP 45/65 GENUS PREMIUM EVO HP 85 GENUS PREMIUM EVO HP 100 GENUS PREMIUM EVO HP 115...
installation The hydraulic system have to be dimensioned and complete with Graph representing the available circulation pump pressure all accessories that ensure the smooth operation. In particular it is necessary to provide all protective equipment and 1000 safety requirements by law. GENUS PREMIUM EVO HP 85/100 is not provided with pump.
installation Discharge of condensation High energy effi ciency produces some condensation which must be removed. To do so, use a plastic pipe placed so as to avoid the accumulation of any condensation inside the boiler. This pipe must be attached to a discharge siphon which can be checked when required.
installation Water circuit diagram Legend: Manual air vent Main heat exchanger Detection Electrode C.H. Flow temperature probe C.H. Return temperature probe Minimum water pressure switch Siphon Circulation Pump (optional for 85/100/115/150) Gas valve 10. Modulating fan 11. Mixer 12. Ignition electrode 13.
installation Connecting the Flue GENUS PREMIUM HP 45/65 The boiler is designed to operate in B mode (by drawing air from is equipped for connection the room) and in C mode (by drawing air from outside). to a 80/125 coaxial fl ue gas When installing an exhaust system be careful when handling the suction and exhaust system.
installation Table of fl ue gas exhaust duct lengths Type of air suction/fl ue gas exhaust ducting Maximum extension Combustion air drawn from the room Diameter exhaust-air (m) External fl ue gas exhaust Type of pipe Air drawn from the room (mm) ø...
L-N poles and the earth connection are all respected. Important! In the event that the power supply cable must be changed, replace it with specifi que cable supply by ARISTON. H05V2V2-F Important! Connection to the electricity mains supply must be...
installation Electrical diagram For increased safety, ask a qualifi ed technician to perform a thorough check of the electrical system. The manufacturer is not responsible for any damage caused by the lack of a suitable earthing system or by the malfunctioning of the electricity mains supply.
commissioning Start-up procedure Initial procedures Press the ON/OFF button on the control panel to switch on the boiler: To guarantee safety and the correct operation of the appliance, the display will light up. the boiler must be prepared for operation by a qualifi ed technician The initialisation procedure - indicated by the bar - begins.
commissioning First ignition Deaeration cycle 1. Make sure that: During the fi lling stage or if there is excess air in the system, The gas valve is closed; the deaeration cycle can be activated by holding the E The electrical connection has been properly carried out. button for 5 seconds.
Once the calibration procedure is completed, analyse the CO2 values at minimum power. GENUS PREMIUM EVO HP 45/65/85/100 Checking the gas setting To carry out analyses of combustion, the cleaning function must be activated.
After these operations, it is advisable to check the gas fl ow on the 57,3 meter, following the instructions outlined in the technical data table. 39,8 GENUS PREMIUM EVO HP 45/65/85/100 34,4 26,9 21,7 19,7 17,3...
commissioning Checking slow ignition power Gas changeover The boiler can be converted to use either methane (natural) gas The soft light can be adjusted between the maximum power and (G20) or L.P.G. ( G31) by an Authorised Service Centre. the minimum power. The display shows the value between “100”...
The various corresponding parameters should therefore be set (see Technical Area). To activate the function, press the AUTO button. For further information please refer to the ARISTON temperature adjustment manual. EXAMPLE 1: SINGLE ZONE SYSTEM (HIGH-TEMPERATURE) WITH ON/OFF ROOM...
boiler protection devices The boiler is protected from malfunctions by means of internal Important If this shutdown occurs frequently, contact an authorised Technical Service checks performed by the electronic P.C.B., which stops the boiler Centre for assistance. For safety reasons, the boiler will permit a maximum of 5 from operating if necessary.
boiler protection devices Anti-frost Device External P.C.B.’s The anti-frost function acts on the central heating fl ow temperature Zone 1 - Room sensor circuit open / short circuit probe, independently from other regulations, when the electrical Zone 2 - Room sensor circuit open / short circuit supply is turned on.
technical area TECHNICAL AREA - reserved for qualifi ed technician Example: Modifi cation of parameter 2.3.1 Max. Adjustable Central Heating Power Accessing the Technical Area allows for setting/confi guring the Proceed as follows: device according to the specifi c requirements of every installation 1.
Page 32
technical area Tecnical Area Service code ( reserved for qualifi ed technicians Turn the encoder and select code 234 and press OK Language, date and time - Follow the instructions of the display. Press OK button at each entry to save COMPLETE MENU - The parameters relating to each individual menu are listed in the following pages.
Page 33
2. 2. 0 Soft ignition from 0 to 100 2 = Modulating 2.2.0 Soft ignition GENUS PREMIUM EVO HP 45/65/85*/100* 60 % *= with Optional Pump Kit (Two speed) 2. 3. 9 Set Delta T Pump from 10 to 30 (°C)
Page 34
technical area description value description value notes notes 2. 5. 7 Anti-legionella Function 0 = OFF 2. 4. 4 Boost Time from 0 to 60 (minutes) 1 = ON Activated with the boiler connected to a tank by an NTC only enabled with Room Thermostat on/off and sensor temperature adjustment activated (parameter 421 or...
Page 35
technical area description value description value notes notes 4. 2. 1 Select Type of 0 = Fixed Flow 4. 2. 4 Room sensor Infl uence from 0 to 20 Thermoregulation Temperature to calculate the set- 1 = Basic point temperature To enabled Thermoreg.
Page 36
technical area description value description value notes notes 6. 2. 2 Zone 3 Slope from 1.0 to 3.5 5. 2. 3 Parallel curve shift Zone from - 14 to + 14 (°C) (high temperature) 2 Off set (high temperature) from 0.2 to 0.8 from - 7 to + 7 (°C) (low temperature) (low temperature)
Page 37
technical area description value notes 8. 2 BOILER 8. 2. 1 Fan Status 0 = OFF 1 = ON 8. 2. 2 Fan Speed - x100 RPM 8. 2. 3 Aperto 8. 2. 4 Diverter valve position 0 = D.H.W. 1 = Central Heating 8.
maintenance Instructions for opening the casing and performing an Instructions for opening the casing and performing an internal inspection (45/65) (85/100/115/150) internal inspection Before performing any work on the boiler, fi rst disconnect it from Before performing any work on the boiler, fi rst disconnect it from the electrical power supply using the external bipolar switch and the electrical power supply using the external bipolar switch and shut off the gas valve.
maintenance Maintenance is an essential part of the safe and effi cient operation are used in conjunction with the anti-scaling and anti-corrosion of the boiler and ensures its durability. It should be performed function, in the quantities suggested by the manufacturer, at the according to the instructions given in current legislation.
maintenance Symbols used on the data plate mbar mbar Legend : 1. Brand 2. Manufacturer 3. Boiler model - Serial number 4. Commercial reference 5. certifi cation number 6. Destination country - gas category 7. Gas setting 8. Installation type 9.