Please Review to ensure you have properly installed this SSAS beacon:
Installed the beacon and bracket on a flat vertical surface in a discreet location. (Paragraph 3.2)
Installed the activation switches. (Minimum of two.)
One must be on the navigation bridge.
Switches shall not be labeled. (Paragraph 3.3.4)
Connected switch wire to switches and terminal block on the top of the mounting bracket. Route
wire appropriately. (Paragraph 3.3.5)
Assembled the antenna using the rods, set screws and wrench provided. (Paragraph 3.4.3)
Installed the antenna in a location at least at least 10 ft (3 m) above deck and with clear view of
the sky using either the included 4" mount or other mount with compatible 1" x 14 threads.
(Paragraph 3.4.4)
Connected antenna to beacon using SMA and TNC connectors provided and RG-8/U coaxial
connector. Route cable appropriately. (Paragraph 3.4.5)
Upon completion of the installation, perform the activation switch (Paragraph 3.3.6) and cross
dipole antenna (Paragraph 3.4.6) installation verification tests.
Upon successful completion of installation verification tests, place the beacon in READY mode.
ADDITIONAL NOTES: