Step 1: Preparing The Site - NETGEAR FS728TPv2 Hardware Installation Manual

Smart poe switch
Hide thumbs Also See for FS728TPv2:
Table of Contents

Advertisement

Step 1: Preparing the Site

Before you install the switch, ensure the operating environment meets the site requirements
in the following table.
Characteristics Requirements
Mounting
• Desktop installations - Provide a flat table or shelf surface.
• Rackmount installations - Use a 19-inch (48.3-centimeter) EIA standard equipment
Access
Locate the switch in a position that allows access to the front-panel RJ-45 ports, view the
front-panel LEDs, and access the power connector.
Power source
Provide a power connection cord. Power specifications for the switch are shown in
Appendix A
accidentally turn off power to the outlet and the switch.
Environmental
• Temperature - Install the switch in a dry area, with ambient temperature between 0 and
• Operating humidity - The installation location should have a maximum relative
• Ventilation - Do not restrict airflow by covering or obstructing air inlets on the sides of
• Operating conditions - Keep the switch at least 6 ft. (1.83 meters) away from nearest
18 |
Chapter 4: Installation
rack that is grounded and physically secure. The rackmount kit supplied with the
switch is also required.
. Ensure the AC outlet is not controlled by a wall switch, which can
50ºC (32ºF and 122ºF). Keep the switch away from heat sources such as direct
sunlight, warm air exhausts, hot-air vents, and heaters.
humidity of 90%, non-condensing.
the switch. Keep at least 2 inches (5.08 centimeters) free on all sides for cooling. Be
sure there is adequate airflow in the room or wiring closet where the switch is
installed.
source of electromagnetic noise, such as a photocopy machine.
FS728TP Hardware Installation Guide

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fs728tp

Table of Contents