End Panel for Trench & Manhole Boxes This booklet is intended to provide basic infonnation for users of the Generation UK Hire End Panel and to draw the client's attention to the aspects of handling, assembly, installation and use which need to be considered in compiling a safe system of work. In particular, the client's attention is drawn to the size and weights of the individual components and the need for planning the lifting operations involved.
Page 3
Typical Assemblies Note: The maximum useable depth is 4.688m. Consisting of 2 No. 2.260m high Panels 1200mm Wide Arrangements 4800 3600 2400 1800 1800mm Wide Arrangements 4800 2400 1200 2400mm Wide Arrangements 3600 1800 Note: End Panels are NOT to be assembled or installed 3No.
Page 4
End Panel for Trench & Manhole Boxes Manpower The Health and Safety Regulations require that personnel deployed are suitably trained, experienced and supervised by a competent person. Plant for Lifting A suitable appliance is required for off-loading and assembly if required. The machine lifting capacity and clearance under the lifting point should be checked against the sizes and weights of the End Panel to be lifted / assembled.
DON'T - Fully extract an End Panel arrangement that is 2no Panels deep. DON'T - Install an End Panel arrangement that exceeds a height of 4688mm. DON'T - Continue to push an End Panel that has slipped or become unstable during installation. IF IN DOUBT CONSULT ALTRAD GENERATION. groundworks.enquiries@altradgeneration...
Page 6
Groundworks Numbers: UK: 087 0870 8484 IRL: 00353 1 601 1500 SCAN ME YOUR LOCAL TO FIND BRANCH Generation UK Ltd. Generation Head Office, Trinity Street, Off Tat Bank Road, Oldbury, West Midlands, B69 4LA - United Kingdom Tel. 0121 543 2950 - Fax. 0121 543 2953 - groundworks.enquiries@altradgeneration.com www.altradgeneration.com...