Installation and Commissioning Manual
M-168.1-SERIE-LT-EN 2024 Version / 06.2024

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Morley IAS LT-159 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Honeywell Morley IAS LT-159

  • Page 1 Installation and Commissioning Manual M-168.1-SERIE-LT-EN 2024 Version / 06.2024...
  • Page 2 No part of this document may be photocopied, reproduced, or translated into another language without the prior written consent of HII. Copyright © 2024 Honeywell International Inc. All rights reserved. Web Address: www.honeywellaidc.com Other product names or marks mentioned in this document may be trademarks or registered trademarks of other companies and are the property of their respective owners.
  • Page 3 This documentation is subject to the copyright of Honeywell. The content must not be copied, published, modified, distributed, transmitted, sold, or changed without the express prior written permission of Honeywell.
  • Page 4 In accordance with Directive 2012/ 19/ EU (WEEE), after being dismantled, electrical and electronic equipment is taken back by the manufacturer for proper disposal. © Honeywell International Inc./ technical changes reserved! This documentation is subject to copyright law and, as per Sections 16 and 17 of the German Copyright Act (UrhG), may be neither copied nor disseminated in any other way.
  • Page 5: Table Of Contents

    Morley IAS | Integrated Fire Alarm Control Panel TABLE OF CONTENTS SECTION 1: ABOUT THIS GUIDE ..........................6 1.1 SCOPE ........................................6 1.2 REVISION HISTORY ..................................6 1.3 INTENDED AUDIENCE ................................. 6 SECTION 2: OVERVIEW ..............................7 2.1 PREREQUISITES ....................................8 2.2 HARDWARE REQUIREMENTS ..............................
  • Page 6: Section 1: About This Guide

    Morley IAS | Integrated Fire Alarm Control Panel SECTION 1: ABOUT THIS GUIDE SCOPE The purpose of this manual is to provide the user with step-by-step instructions related to the installation, commissioning, and troubleshooting of the Integrated Fire Alarm Control Panel, AGILE Wireless Devices, Connected Life Safety Services (CLSS) gateway, and Cloud application configuration.
  • Page 7: Section 2: Overview

    Morley IAS | Integrated Fire Alarm Control Panel SECTION 2: OVERVIEW The Integrated system consists of three main components. They are: 01. Fire Alarm Control Panel: The (LT- 159) Fire Alarm Control Panel (FACP) has analog addressable capabilities. It is designed for AGILE wireless equipment.
  • Page 8: Prerequisites

    Download the Honeywell AGILE IQ software from: https://systemsensoreurope.com/products/AGILE-wireless-software-suite/ 2.4 CLSS CREDENTIAL REQUIREMENTS • Request login access from Honeywell, Connected Life Safety Services website: https://fire.honeywell.com/#/signup • CLSS login credentials are required to configure the user accounts. Installation and Commissioning Manual | 1.0...
  • Page 9: Section 3: Installing The Fire Alarm Control Panel (Facp) And Clss

    Morley IAS | Integrated Fire Alarm Control Panel SECTION 3: INSTALLING THE FIRE ALARM CONTROL PANEL (FACP) AND CLSS This section provides an overview of the parts and installation of the panel and CLSS gateway. PRECAUTIONS Before installing the panel, follow these precautions: •...
  • Page 10: Installing The System

    Morley IAS | Integrated Fire Alarm Control Panel INSTALLING THE SYSTEM This section describes how to unbox the panel, install the back plate, and terminations, and mount the panel on the wall. UNBOXING THE PANEL AND INSTALLATION 3.2.1. 01. Remove the panel cover screws (12) safely from the panel as shown in the figure. Front Cover USB Port B Type LED Indicators...
  • Page 11 Morley IAS | Integrated Fire Alarm Control Panel 04. Remove the knockouts to fit the back plate a. Detach the knockouts from the panel to b. Secure the back plate in the desired mount the back plate. location. 05. Mount RS 485 Connector. 06.
  • Page 12 Morley IAS | Integrated Fire Alarm Control Panel 08. Mount the panel base in the desired location and secure it with a screw. b. Drill and make four holes through the on the wall as per the dimensions position of the hole marked. shown in the diagram.
  • Page 13 Morley IAS | Integrated Fire Alarm Control Panel 13. Reinstall the PCB to the panel. 14. Terminate the wires into the respective terminals as shown in the figure. 15. Terminate the panel power cable with a Type G adapter. 16. Terminate AGILE gateway loop wire. 17.
  • Page 14 Morley IAS | Integrated Fire Alarm Control Panel 18. Connect RS-485/ CLSS gateway communication into the serial port 1 as shown in Figure (a) and fix the panel batteries in the respective slots as shown in Figure (b). CLSS GATEWAY INSTALLATION AND TERMINATIONS 3.2.2.
  • Page 15 Morley IAS | Integrated Fire Alarm Control Panel 01. Mount the CLSS gateway with the screws. 02. Remove the required knockouts to route the wires. 03. As shown in the figure, connect the CLSS gateway with a 24V power adapter and output power to the RS-485 converter.
  • Page 16: Configuring The Agile Wireless Devices

    Morley IAS | Integrated Fire Alarm Control Panel CONFIGURING THE AGILE WIRELESS DEVICES 01. Set AGILE Gateway Address and mount into the base. 02. Set all AGILE wireless device addresses. 03. Set the unique address for wireless devices. 04. Install the four batteries in the given slot and mount them into the base. 05.
  • Page 17: Section 4: Commissioning The Fire Alarm Control Panel (Facp)

    AGILEIQ Honeywell Morley IAS will be displayed on the desktop. 04. Plug in the Wireless USB Dongle to your Laptop/ PC. NOTE: The trial version of AGILE IQ Honeywell Morley IAS software is valid only for one month. Kindly contact the respective vendor to purchase the software license.
  • Page 18 Morley IAS | Integrated Fire Alarm Control Panel 07. Choose the Path where you want to save the mesh file and enter the desired file name. 08. Click the Button. 09. A pop-up window prompts, you want to add an image of the 10.
  • Page 19 Morley IAS | Integrated Fire Alarm Control Panel 11. Double-click on the displayed gateway to set the address that you have physically assigned. 12. Choose the relevant device type icon. 13. Click on the configuration management area to add the chosen device. 14.
  • Page 20 Morley IAS | Integrated Fire Alarm Control Panel 15. Click the metric to map the meter reference for the first device nearest to the gateway. NOTE: Set the actual distance from the gateway to nearest device. The distance must be less than 10 mts. 16.
  • Page 21 Morley IAS | Integrated Fire Alarm Control Panel 19. Set the RF channel and click NOTE: The application switches to Pre- commissioning mode. 20. Click Start the Gateway Pre-commissioning Wizard. Installation and Commissioning Manual | 1.0...
  • Page 22 Morley IAS | Integrated Fire Alarm Control Panel 21. The following Gateway Pre-commissioning Wizard will be displayed. 22. Choose Option [A] For a fresh commission proceed with the pre-commissioning steps. (or) 23. Choose Option [B] If the configured devices already exist on the network when the devices are: Failed or interrupted Reusing the same devices...
  • Page 23 Morley IAS | Integrated Fire Alarm Control Panel 26. Click the "START" button to verify device communication. NOTE: This action will initiate the process to check the devices communication. 27. Once the communication of the devices is successful, click to begin commissioning. 28.
  • Page 24 Morley IAS | Integrated Fire Alarm Control Panel 29. Select then commissioning starts. Refer to the AGILE manual for more information, 30. After commissioning, a pop-up display with "All devices commissioned". NOTE: If any issues arise during mesh creation, follow the instructions in the pop- up or refer to the AGILEIQ manual.
  • Page 25 Morley IAS | Integrated Fire Alarm Control Panel 33. The wireless devices reported a n fault on the panel screen. Installation and Commissioning Manual | 1.0...
  • Page 26: Panel Controls And Functions

    Morley IAS | Integrated Fire Alarm Control Panel PANEL CONTROLS AND FUNCTIONS This section describes controls, functions, and descriptions along with the commissioning of the Morley Lite Panel. LED Indicators Functional Buttons Touch Display Icon Controls and Color Descriptions of Integrated Fire Alarm Control Panel. STATUS CONDITION / CONTROL COLOR...
  • Page 27 Morley IAS | Integrated Fire Alarm Control Panel STATUS CONDITION / CONTROL COLOR DESCRIPTION ICON POWER FAULT Yellow Mains fault (blinking) batteries) Yellow (fixed) Batteries fault POWER Green (fixed) The system is switched on and the power is supplied via the mains Push Buttons Descriptions and Functions PUSH...
  • Page 28: Panel Commissioning

    Morley IAS | Integrated Fire Alarm Control Panel PANEL COMMISSIONING To program, access the system configuration, as shown below. 01. On the touchscreen display, press the arrow on the right and then press the gear icon at the top right. 02.
  • Page 29 In case, you forget the password, click on Forget Passcode option. A recovery passcode screen displays a 20- character alpha- numeric recovery key. Contact Honeywell Technical Service and share the key, to recover the level 3 passcode. Installation and Commissioning Manual | 1.0...
  • Page 30: Creating Xml File From The Panel

    Morley IAS | Integrated Fire Alarm Control Panel CREATING XML FILE FROM THE PANEL This section describes the step-by-step procedure to generate an XML file required for the Device List Tab in the CLSS Site Manager. Follow each step to ensure precise configuration and creation of the XML file.
  • Page 31 Morley IAS | Integrated Fire Alarm Control Panel 04. Click and expand the section. 05. Enter the level- 3 password in the designated field. 06. Click t h e button to establish a connection with the panel. 07. Click t h e button to download the current configuration from the panel to the PC tool application.
  • Page 32 Morley IAS | Integrated Fire Alarm Control Panel 08. Expand the zones section to configure the zone label. 09. Expand the section to configure device location/ zone number. 10. Click on the save button to save the data locally. 11. Click the button to return the updated configuration to the panel.
  • Page 33: Creating Customer Profiles And Managing Sites

    To create a new site and add Villa, proceed with the following steps: 01. Switch ON CLSS Gateway. 02. Login with the site manager account using this URL: https://fire.honeywell.com/#/signup create the customer profiles and manage the remote sites. 03. Close any notifications and click &...
  • Page 34 Morley IAS | Integrated Fire Alarm Control Panel 05. Fill in the required details on the page and click on t h e button. 06. Upon saving, the customer profile and a Villa will be automatically created. Installation and Commissioning Manual | 1.0...
  • Page 35 Morley IAS | Integrated Fire Alarm Control Panel 07. To add more villas under the same site, click the button. 08. Enter the villa details and click & Installation and Commissioning Manual | 1.0...
  • Page 36 Morley IAS | Integrated Fire Alarm Control Panel 09. Save the configuration. Now the site manages multiple Villas. 10. Navigate to "All Customers" and search for the desired site. 11. Select the villa where you want to upload the configuration file and click on the "Apply" button. Installation and Commissioning Manual | 1.0...
  • Page 37 Morley IAS | Integrated Fire Alarm Control Panel 12. Click on "Device List". 13. Select "Upload Device List". Choose the "Upload Device List" option and select the Morley IAS panel Brand. Installation and Commissioning Manual | 1.0...
  • Page 38 Morley IAS | Integrated Fire Alarm Control Panel 15. Choose the XML file from the saved folder and click the "Import" button. 16. Click "Close" after the devices are successfully uploaded. 17. The uploaded devices list will be displayed on the site. Installation and Commissioning Manual | 1.0...
  • Page 39: Creating Community Supervisor Account

    Morley IAS | Integrated Fire Alarm Control Panel CREATING COMMUNITY SUPERVISOR ACCOUNT 01. Click "Manage Contacts". 02. Click "Add New Contacts" on the Contacts page. 03. Enter the required contact information on the "Add Contact" page. Installation and Commissioning Manual | 1.0...
  • Page 40 Morley IAS | Integrated Fire Alarm Control Panel 04. Click "Save & Next" to switch to the "Choose Subscriptions" tab. Select the appropriate subscriptions and click on "Save & Next". 05. Choose the "Assign Sites & Villas" tab and assign the specific villa to the new community supervisor then click "Save &...
  • Page 41 Morley IAS | Integrated Fire Alarm Control Panel 06. Click "Save & Close". The added contact details page will open. 07. Click "Close" to update the contact details in the customer details section. 08. Check the email specified during the contact addition process. The community supervisor account details (username and password) will be sent to this email.
  • Page 42: Clss Gateway Configuration For Morley Panel

    Morley IAS | Integrated Fire Alarm Control Panel CLSS GATEWAY CONFIGURATION FOR MORLEY PANEL Follow these steps to install the Fixed Gateway using the Connected Life Safety Service (CLSS) mobile application. 01. Download and install the Connected Life Safety Service mobile app from the Google Play Store for Android mobile / App Store for IOS mobile devices.
  • Page 43 Morley IAS | Integrated Fire Alarm Control Panel 08. Click t h e "Login" button. 09. On the Sign-in page, enter the Site Manager credentials, c l i c k "Sign in" and enter the password on the next page. Installation and Commissioning Manual | 1.0...
  • Page 44 Morley IAS | Integrated Fire Alarm Control Panel 10. Select "Install Fixed Gateway" from the displayed options. 11. Search for your name and select it. Choose the appropriate site from the list, and then select the Villa. Installation and Commissioning Manual | 1.0...
  • Page 45 Morley IAS | Integrated Fire Alarm Control Panel 12. The app starts discovering gateways. Select your respective gateway from the list by referring to the ownership code. 13. Ensure the Panel Brand and Connection are set to "MORLEY- IAS Standard Protocol". Installation and Commissioning Manual | 1.0...
  • Page 46 Morley IAS | Integrated Fire Alarm Control Panel 14. Click the "NEXT" button to start applying configuration data and panel connection for the Connected Life Safety Service. 15. The Success message is displayed. Click t h e "OK" button. 16. On the next screen, click the "PROCEED" button, select the panel, and then t h e "Done" button. The gateway connection status will be visible on the Site dashboard.
  • Page 47: Removing The Panel

    Morley IAS | Integrated Fire Alarm Control Panel REMOVING THE PANEL FRONT COVER Before working on the FACP, remove the panel front cover. 01. Remove the plastic cover on the touch screen. 02. Connect the display ribbon cable, fix the front cover, and remove the plastic attached to it as shown in the figure.
  • Page 48: Section 5: Support

    TROUBLESHOOTING SCENARIOS This section outlines various scenarios that may arise during installation and commissioning, along with the corresponding corrective measures. These scenarios can be handled using the following corrective actions or by contacting Honeywell Technical Support. S. No Description Corrective Actions...
  • Page 49: Technical Support

    Confirm the EOL resistor installation in the RS-485 port at the CLSS Gateway (Wi-Fi or Ethernet) TECHNICAL SUPPORT For any technical-related queries contact Honeywell Building Technologies customer support. Technical Support E-mail: fire.ts.meta@honeywell.com Customer Service Email: fire.cs.mea@honeywell.com Installation and Commissioning Manual | 1.0...

Table of Contents