Sleipner PRO SEP60 Installation Manual

Pro ignition protected dc thruster

Advertisement

Quick Links

Installation Guide
For Pro Ignition Protected DC Thruster Models
SEP-IP60
DOCUMENT ID:
4354
REVISION:
17
DATE:
2024
EN
LANGUAGE:

Advertisement

loading
Need help?

Need help?

Do you have a question about the PRO SEP60 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Sleipner PRO SEP60

  • Page 1 Installation Guide For Pro Ignition Protected DC Thruster Models SEP-IP60 DOCUMENT ID: 4354 REVISION: DATE: 2024 LANGUAGE:...
  • Page 2 Failure to follow instructions within this document will render all warranties given by Sleipner Motor as VOID. Warnings and situations requiring extra caution are outlined in the documentation. Take extra consideration when warnings are outlined.
  • Page 3 Ensure that you operate with high-quality batteries intended for maritime use. • All Sleipner proportional thrusters will work well with Lithium batteries, as the included PPC unit will control the output voltage to safe levels for the thruster. (NB: Ensure you have the latest embedded software installed. The fi rmware version of the Proportional Power Controller (PPC) must be of version 1.033 or later if the PPC is connected to a lithium battery).
  • Page 4 Ignition Protection MC_0482 Sleipner develops IP (Ignition Protected) products suitable for marine engine compartments and fuel tank spaces. Combination products sold as complete systems may combine IP and non-IP items. CAUTION The installer is responsible for identifying ignition-protected and non-ignition-protected products when considering installation locations.
  • Page 5 Product Dimensions MC_0130 SE IP 60 SE IP 60 Measurement Measurement description code mm inch mm inch Internal tunnel diameter 7,28 7,28 Motor Height 12,64 12,64 Width 9,13 9,13 Length 10,71 10,71 Water Depth 7,28 7,28 Minimum tunnel length 5,04 5,04 TL (recommended) Recommended tunnel length...
  • Page 6 Product Clearance Requirements MC_0672 This product has clearance considerations extending the base product footprint. Follow the clearance requirements when planning your installation. A minimum clearance of 90mm above the thruster is required for the control cable MG_0592 Product Specifi cations MC_0506 Thrust at Thrust at...
  • Page 7 Positioning of the tunnel / thruster MC_0003 1. Aim to install the thruster as far forward as possible Due to the leverage effect around the boats’ pivot point. The distance difference from the boat pivots’ point to the thruster will determine the amount of real rotation power for the boat.
  • Page 8 Tunnel Length MC_0003 Optimal tunnel length Achieving the correct tunnel length depends on many factors from the hull type, operation and environmental conditions. Tunnels should avoid being longer than 4 x the tunnel diameter as this will reduce thruster performance. (NB: Installing long length tunnels can flex/ bend over time and may require additional support.
  • Page 9 Tunnel installation in Sailboats MC_0003 Some sail boats have a flat bottom and shallow draft in the bow section. This can make installing the thruster as far forward from the boats main pivot point diffi cult. However, it is possible to install a tunnel thruster in most sail boats, even when the hull does not directly support the fi tting of a tunnel. Instead fi t the tunnel halfway into the underneath section of the existing hull.
  • Page 10 Water Deflection MC_0003 A possible problem in sail boats or fast powerboats is that a non-rounded surface can generate drag from the back face of the tunnel, as it creates a “flat” area facing the flow of water. This problem can be solved in two different ways, depending on what is possible or easier to perform. The best solution which generally reduces the most drag is to make a recess in the hull at the back of the tunnel.
  • Page 11 This “free” extra thrust in optimal installations be 30 - 40% of the total thrust. (NB: A Sleipner thruster propeller does not produce cavitation at working speed. Therefore, any cavitation and cavitation noise in the tunnel will be caused during improper tunnel installation.)
  • Page 12 Tunnel Installation MC_0003 The following are only general instructions and do not explain in any way the details of fi breglass work. Problems caused by faulty installation of the tunnel, are the installers full responsibility. Seek a professional boat builder when modifying the hull. Find the position in the boat considering the information earlier in this manual and the applicable measurements for the thruster model you are installing.
  • Page 13 You must apply gel coat to areas you have grounded/ moulded to make waterproof. These areas allow water access to the hull which is typically not waterproof without these applications outside. (NB: All original Sleipner tunnels are fully waterproof when delivered except in the areas where you have cut and bonded it to the hull.)
  • Page 14 Stern Tunnel Installation MC_0003 For Stern Thruster installation please refer to the supplied manual in your Sleipner product delivery Installation Guide For DC Electric Thruster Models SE80, SE100, SE120, SE130, SE150 Stern Thruster SLEIPNER AS DOCUMENT ID: 222222 REVISION: P.O. Box 519...
  • Page 15 Gear Leg & Motor Bracket Installation MC_0258 Please refer to the graphic for special considerations relating to your model Mark the tunnel centreline and the boat’s centreline. (NB: Install the gear leg and propeller as shown for the thrust direction to correspond with the control panel.) Use the gasket or template (recommended) to mark the hole centres and double-check the measurements.
  • Page 16 Gear Leg & Motor Bracket Installation MC_0258 Please refer to the graphic for special considerations relating to your model Place the gear leg (without the propeller) with the gasket on inside the tunnel. Place the propeller on the gear leg (NB: Do not secure the propeller with securing parts) to ensure it is centred and rotates freely with the same clearance from each blade to the tunnel wall.
  • Page 17 Gear Leg & Motor Bracket Installation MC_0258 Please refer to the graphic for special considerations relating to your model Apply appropriate sealant to both sides of the gasket and place on the gear leg. Place the gear leg in the tunnel (without the propeller). Use appropriate sealant to ensure that no leakages occur.
  • Page 18 Propeller Installation MC_0018 Centre the drive pin and insert the propeller onto the shaft spine. Rotate the propeller until the drive pin aligns with the internal slot in the propeller. Insert the washer and tighten the propeller lock-nut to secure the propeller. Insert the anode into the propeller and tighten the anode holding screw.
  • Page 19 Motor Installation MC_0043 Please refer to the graphic for special considerations relating to your model Insert the drive pin to the motor drive shaft. Insert the coupling to align with the drive pin in the motor shaft. Install the motor onto the motor bracket ensuring the couplings are engaged together correctly (top and bottom). (NB: The motor can be placed in all directions on the motor bracket.
  • Page 20 Proportional Power Controller (PPC) and thruster motor, see Wiring Diagram chapter for an overview. Sleipner offers both manual main switches and Automatic Main Switches (AMS). Sleipner AMS is controlled by the control panel in addition to the option of manual operation.
  • Page 21 Product Lug Connection Configuration Spring Lugs washer Tighten to Isolation Cap 18Nm (13.8lb/ft) Washer Hold in place for securing the end nut. Multi-lug configuration CAUTION Ensure lug faces Do not use washers between lugs, this causes are back to back. overheating and fire.
  • Page 22 Manual Main Switch Wiring Diagram 12V S-Link IP Thruster The Top wiring setup is for a single bow OR stern thruster system See S-Link System Description chapter for detailed Control information on installation of S-Link POWER Cable, panel END Terminator and additional S-Link components. S-Link Backbone cable S-Link Spur cable ANL Fuse...
  • Page 23 Automatic Main Switch Wiring Diagram 12V S-Link IP Thruster The Top wiring setup is for a single bow OR stern thruster system See S-Link System Description chapter for detailed Control information on installation of S-Link POWER Cable, panel END Terminator and additional S-Link components. S-Link Backbone cable S-Link Spur cable Automatic Main Switch...
  • Page 24 Manual Main Switch Wiring Diagram 24V S-Link IP Thruster The Top wiring setup is for a single bow OR stern thruster system See S-Link System Description chapter for detailed Control information on installation of S-Link POWER Cable, panel END Terminator and additional S-Link components. S-Link Backbone cable S-Link Spur cable ANL Fuse...
  • Page 25 Automatic Main Switch Wiring Diagram 24V S-Link IP Thruster The Top wiring setup is for a single bow OR stern thruster system See S-Link System Description chapter for detailed Control information on installation of S-Link POWER Cable, panel END Terminator and additional S-Link components. S-Link Backbone cable Automatic Main Switch S-Link Spur...
  • Page 26 MC_0120 S-Link is a CAN-based control system used for communication between Sleipner products installed on a vessel. The system uses BACKBONE Cables as a common power and communication bus with separate SPUR Cables to each connected unit. Only one S-Link POWER cable shall be connected to the BACKBONE Cable.
  • Page 27 Control Panel Installation MC_0398 For Control Panel installation please refer to the Installation Guide accompanying the control panel to be installed. Installation Guide Control Panel SLEIPNER MOTOR AS DOCUMENT ID: REVISION: P.O. Box 519 N-1612 Fredrikstad DATE: Norway www.sleipnergroup.com LANGUAGE:...
  • Page 28 Post installation checklist MC_0033 []..The bolts holding the gear leg and main bracket together are tightened correctly. []..The bolts holding the motor to its bracket are tightened correctly. []..All electrical connections are clean, dry and tight, and the correct cable, fuse and main switch size.
  • Page 29 11. This warranty gives you specific legal rights, and you may also have other rights which vary from country to country. Patents MC_0024 At Sleipner we continually reinvest to develop and offer the latest technology in marine advancements. To see the many unique designs we have patented visit our website www.sleipnergroup.com/patents SEP IP 60...
  • Page 30 Notes MC_0037 ..............................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................SEP IP 60 4354 2024...
  • Page 31 Notes MC_0037 ..............................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................SEP IP 60 4354 2024...
  • Page 32 © Sleipner Group, All rights reserved The information given in the document was right at the time it was published. However, Sleipner Group cannot accept liability for any inaccuracies or omissions it may contain. Continuous product improvement may change the product specifi cations without notice.