Series ii Series ii NATURAL TO PROPANE CONVERSION INSTRUCTIONS Models TRX150 TRX199 TRX199C WARNING This conversion kit shall be installed by a qualified installer, service agency, or the gas supplier in accordance with the manufacturer’s instructions and all applicable codes and requirements of the authority having jurisdiction.
Part 0. General Safety information NTI boilers are factory set to operate IF THE KIT CONTENTS DO NOT with Natural Gas. MATCH THOSE SPECIFIED FOR YOUR BEFORE OPERATING WITH PROPANE BOILER MODEL (SEE TABLE 1), DO the boiler must be converted to Propane...
Page 3
Contact NTI for the Natural Gas to installed in a pit or similar location LP conversion kit and instructions for that will permit heavier than air gas other models.
Page 4
Part 1. Installation and Preset Procedure 1. Install LP-Mixer with g. Remove the three bolts securing the NG-mixer to the blower and remove the LP-Diaphragm NG-Mixer. a. Check that the code of the air / gas mixer and the diameter of the gas diaphragm are those indicated for the model of boiler to be converted –...
Page 5
Part 1. Installation and Preset Procedure i. Reassemble the gas pipe to the gas valve and mixer. ATTENTION!! USE THE NEW RUBBER GASKETS PROVIDED WITH THE KIT. j. Install the silencer. 2. Perform preliminary adjustment on gas valve throttle screw 4. a.
Page 6
Part 2. Operation Sequence and Gas Line Pressure Check f. Observe the line pressure with the boiler WARNING running, while checking/ adjusting the CO2 at maximum and minimum gas flow Failure to perform the Gas Valve rate (see Part. 3). and Burner Setup correctly may Compare it to Table 2.
Page 7
Part 3. Combustion Check and Calibration WARNING Adjustments to the Gas valve may only be made by a qualified gas technician, while using a calibrated combustion analyzer capable of measuring CO2 and CO. Adjustments may only be performed if the gas line pressure is maintained above minimum levels...
Page 8
Part 3. Combustion Check and Calibration 2. Checking/Adjusting the CO2 at Note: BURNER TEST Max Power (100%) To activate the BURNER TEST access to Set the thermostat at the highest the Test Mode Menu. possible setting or draw off the domestic Press the MENU button.
Page 9
Part 3. Combustion Check and Calibration ATTENTION!! NOTE: The CO2 reading at Min Power must VALUES MUST BE OBTAINED WITH THE be set lower than the CO2 reading at Max FRONT COVER INSTALLED. Power by 0.5-1.0% If the CO2 reading differs from the values ADJUSTING THE GAS VALVE AT MIN given in the table, then adjust the gas POWER (10%)
Page 10
Part 3. Combustion Check and Calibration Model Min Power Max Power Burner Power Burner Power TRX 150 15.0 10 % 100% TRX 199 / 199C 19.2 1. Canada: Altitudes between 2000-4500 ft, de-rate by 10%. Consult local authorities for de-rating for altitudes above 4500ft. 2.
Page 11
Part 4. Document the Conversion 1. Update rating plate As the certified installer of the Natural Gas to LP Conversion Kit, you must indicate on the boiler that it has been converted for use with Propane (LP) Gas: a. Update Rating Plate Decal – Locate the rating plate decal on the side of the appliance.
Page 12
NTI Boilers Inc. 30 Stonegate Drive Saint John, NB E2H 0A4 Canada Technical Assistance: 1-800-688-2575 Website: www.ntiboilers.com Fax: 1-506-432-1135 Visit us online 420022002700 - Rev. 02 - 031324...