Step 1 - Inspect Shipment. 1
Step 2 - Rig and Place Unit. I
• RIGGING
Step 3 - Check Compressor Mounting
and Connections. 3
Page
TROUBLESHOOTING GUIDE.14,15
SAFETY CONSIDERATIONS
Installation, start-up and servicing of this
equipment can be hazardous due to system pres¬
sures, electrical components and equipment
location (roofs, elevated structures, etc.).
Only trained, qualified installers and service
mechanics should install, start-up and service
this equipment.
When working on the equipment, observe pre¬
cautions in the literature, tags, stickers and labels
attached to the equipment and any other safety
precautions that apply.
• Follow all safety codes.
• Wear safety glasses and work gloves.
• Use care in handling, rigging and setting bulky
equipment.
INSTALLATION
Step 1 - Inspect Shipment
Inspect unit for damage or missing parts. If dam¬
age is detected, or if shipment is incomplete, file a
claim immediately with the shipping company.
Step 2 - Rig and Place Unit
RIGGING
On each end of cooler, a steel loop is provided for
the preferred method of lifting unit. Use spreader
bars to keep cables away from compressor enclo^
sure and control box. If unit is to be moved by fork
truck, use the following methods:
1. From front or rear, lift under the cooler rails.
Unit can be either on or off skid.
2. When moving from ends, leave unit on skid. Lift
from under skid.