GE Innova Series Manual page 32

Single plane and biplane pre–installation kit installation procedures
Table of Contents

Advertisement

GE Healthcare
4.2.3 Safety
4.3 Procedure
1. Refer to
PIST0002 - Prepare Floor - LC Base Plate and Omega/InnovaIQ
2. Refer to illustration below:
32
Single Plane and Biplane Innova Systems Pre–Installation Kit Installation Procedures
WARNING
PERSONAL INJURY DUE TO IMPROPERLY MOUNTED EQUIPMENT!
AVOID POTENTIAL THROUGH–BOLT MOUNTING FAILURES BY HAVING THE
HOSPITAL STRUCTURAL ENGINEER OR ARCHITECT VERIFY THE FLOOR
CONSTRUCTION BEFORE DRILLING HOLES. PAN–TYPE FLOOR
CONSTRUCTION REQUIRES THE USE OF SPECIALLY DESIGNED BENEATH–
THE–FLOOR STEEL CHANNELS TO ENSURE THE THROUGH–BOLT
MOUNTING HARDWARE DOES NOT FAIL DURING USE. THESE CHANNELS
MUST BE DESIGNED BY AN AUTHORIZED LOCAL STRUCTURAL ENGINEER.
AVOID POTENTIAL FLOOR ANCHOR FAILURES BY HAVING THE HOSPITAL
STRUCTURAL ENGINEER OR ARCHITECT INSPECT THE COMPRESSION
STRENGTH OF THE CONCRETE FLOOR BEFORE USING FLOOR ANCHORS.
THE MAXIMUM PULLOUT FORCE PER ANCHOR WA CALCULATED
ASSUMING A REGULAR WEIGHT CONCRETE HAVING A MINIMUM
COMPRESSION STRENGTH OF 2500 PSI (176 KG/CM2) AT THE TIME OF
INSTALLATION, AND ANCHORS INSTALLED TO THE REQUIRED HOLE
DEPTH. ENSURE THE CONCRETE FLOOR MEETS THIS MINIMUM
COMPRESSION STRENGTH BEFORE USING FLOOR ANCHORS.
Direction 2290880-12-1EN, Revision 1
4 PIST0005 - Floor Anchor Mounting On Grade