S-50 Field Installation Manual INDEX Important Instructions……………………………………………………………… Product Specifications…………………………………………………..…………. Unpacking & Mounting …………………………………………………………… Connection Type 1 ……………………………………………………………..…… Connection Diagram............... 6 Connection Type 2 ……………………………..……………………………… Connection Type 3 ……………………………………………………….…………. Electrical Data Sheet ………………………………………..…………………….. Recommended Part List………………………………………………..…..…….. ______________________________________________________________________________________...
Any warning provided by Celec must be passed through to the end user. Celec offers a warranty only as to the quality of its product to confirm to the catalog specifications. No other warranty is offered. Celec assumes no liability for any personal injury, property damage, losses or claims arising out of the misapplication and Non performance of its products.
CAUTION Indoor Use Only, Type-1 Enclosure. 1. Choose the dry and Clean Floor to Install the S-50 taking care conduit connections from Bottom side Enclosure Size is 800 x 1000 x 300 mm and weight 84kg (186 Pounds). 2. Premark the Mounting holes on floor or structure.
1.11 Using panel key open the door of S-50 exposing connections. 1.12 Locate Earth Terminal in S-50, connect the earth wire to S-50 Earth Terminal. Connect the other side of earth wire to main breaker panel ground rod. Ensure all mechanical connections are secure and making full contact.
S-50 unit is designed for use with Customer Main Breaker Panel Three Phase 208V AC WYE/Delta Connection, up to 1600 Ampere. S-50 units should be mounted with appropriate sized fasteners before connect to Main Breaker Panel. Using panel key open the door of S-50 exposing connections.
2. Wire in rigid conduit between customer main breaker panel & external disconnect switch. 3. Locate earth ground connection in S-50 and connect to grounding bar or to earth ground rod in main breaker panel.
S-50 Field Installation Manual Electrical Data Sheet Model S-50 Phase Configuration Three Phase 208V AC WYE/Delta Maximum Line Voltage 208V AC Maximum Power 50 kVar Steps Monitoring PF, kVA, kVar, Volt, Current, KW, %THD-V Internal Temperature & Capacitor Status Accuracy...
Installation of material and workmanship at the customer’s Main Breaker Panel shall be the responsibility of the qualified Electrician in accordance with NEC. Any and all connections exterior to the S-50 unit shall be the responsibility of the qualified Electrician. ______________________________________________________________________________________...