2.
INSTALLATION
2.1
Points To Consider
Plan your installation before mounting any Allegro Linear 2.1 AC. The following
should be considered for a successful installation:
•
Weather conditions and ambient temperature of installation site.
•
Installation distances and appropriate cable lengths. Please consult your local Traxon™
office or authorized agent for necessary aid.
•
The number of Allegro Linear 2.1 AC and appropriate power sources.
•
Distance between each Allegro Linear 2.1 AC for thermal expansion.
•
Proper surge protection.
2.1.1
Installation Checklist
1.
Prepare cables and all necessary accessories.
2.
Perform functional check of Allegro Linear 2.1 AC. Take care not to damage cables/
connectors during pre-installation checks.
3.
Ensure all pre-installation checks laid out below have been followed.
4.
Mount the Allegro Linear 2.1 AC on-site. If the installation is to be left uncompleted
overnight, place all non-connected LED Engines and Allegro Linear 2.1 AC in an indoor
environment.
Ensure all the Interconnection Cables, Allegro Linear 2.1 AC and power
sources are initially stored in a dry area to guarantee the complete sealing of
the system from water before installation.
www.traxon-ecue.com
Installation Guide
©2023 TRAXON TECHNOLOGIES. ALL RIGHTS RESERVED.
07/23 V1.1
8 of 19