pressure can be regulated in order to optimize use of air-powered tools
operating on the knob with the valve open (pulling it up and turning it in a
G
clockwise direction to increase pressure and counterclockwise to reduce
this) (fig. 8). Once you have set the value required, push the knob down to
lock it.
B
• The value set can be checked on the gauge (for versions equipped with
this, fig. 9).
• Please check that the air consumption and the maximum working
pressure of the pneumatic tool to be used are compatible with the
pressure set on the pressure regulator and with the amount of air
supplied by the compressor.
• When you have finished working, stop the machine, pull out the plug and
empty the reservoir.
AIR RECEIVER (ON TANK-MOUNTED UNITS)
3
• Corrosion must be prevented: depending on the conditions of use,
condensate may accumulate inside the tank and must be drained every
day. This may be done manually, by opening the drain valve, or by means
of the automatic drain, if fitted to the tank. Nevertheless, a weekly check of
correct functioning of the automatic valve is needed. This has to be done
by opening the manual drain valve and check for condensate (fig. 13).
• Periodical service inspection of the air receiver is needed, as internal
corrosion can reduce the steel wall thickness with the consequent risk
of bursting. Local rules need to be respected, if applicable. The use of
the air receiver is forbidden once the wall thickness reaches the minimum
value as indicated in the service manual of the air receiver (part of the
documentation delivered with the unit).
• Lifetime of the air receiver mainly depends on the working environment.
Avoid installing the compressor in a dirty and corrosive environment, as
this can reduce the vessel lifetime dramatically.
• Do not anchor the vessel or attached components directly to the ground
or fixed structures. Fit the pressure vessel with vibration dampers to avoid
possible fatigue failure caused by vibration of the vessel during use.
• Use the vessel within the pressure and temperature limits stated on the
nameplate and the testing report.
• No alterations must be made to this vessel by welding, drilling or other
mechanical methods.

MAINTENANCE

4
• The service life of the machine depends on maintenance quality.
• PRIOR TO ANY OPERATION SET THE PRESSURE SWITCH TO THE
OFF POSITION, PULL OUT THE PLUG AND COMPLETELY DRAIN THE
RESERVOIR.
• Check that all screws (in particular those of the head of the unit) are
tightly drawn up (fig. 10). The check must be carried out prior to the first
compressor starting.
POSSIBLE FAULTS AND RELATED PERMITTED REMEDIES
5
Request the assistance of a qualified electrician for operations on electric components (cables, motor, pressure switch, electric panel, etc).
FAULT
Air leak from the valve of the pressure switch.
Reduction of efficiency, frequent start-up. Low
pressure values.
+7 (800) 777-83-75(звонок бесплатный)
www.v-p-k.ru
Screw M6
Screw M8
Screw M10
Screw M12
Screw M14
• Clean the suction filter according to the type of environment and in any case
at least every 100 hours. If necessary, replace the filter (a clogged filter
impairs efficiency while an inefficient filter causes harsher wear on the
compressor (figures 11a - 11b).
• Change the oil after the first 100 hours of operation and subsequently every
300 hours. Check the oil level periodically.
• Use API CC/SC SAE 40. (For cold climates, API CC/SC SAE 20 is
recommended). Never mix different grade oils. If the oil changes color
(whitish = presence of water; dark = overheated), it is good practice to
replace the oil immediately.
• After topping up, tighten the plug (fig. 12) making sure that there are no
leaks during use. Once a week, check the oil level to assure lubrication in
time (fig. 7a).
• Periodically, check the tension of the belts which must have a flexion (f) of
around 1 cm (fig. 14).
FUNCTION
Cleaning of intake filter and/
or substitution of filtering
element
Change of oil*
Tightening of head tension
rods
Draining tank condensate
Checking the tension of
the belts
*
Spent oil and condensate MUST BE DISPOSED OF in compliance with
protection of the environment and current legislation.
The compressor must be disposed in conformity with the methods
provided for by local regulations
CAUSE
Check valve does not perform its function
correctly due to wear or dirt on the seal.
Condensate drainage cock open.
Rilsan hose not inserted correctly in pressure
switch.
Excessively high consumption.
Leaks from joints and/or pipes.
Clogging of the suction filter.
Slipping of the belt.
TABLE 1 – TIGHTENING OF HEAD TENSION RODS
Nm
Min. torque
9
22
45
76
121
TABLE 2 – MAINTENANCE
AFTER THE
FIRST 100
HOURS
The check must be carried out prior to the first
compressor starting.
Daily
Periodically
Unscrew the hex-shaped head of the check
valve, clean the housing and the special rubber
disk (replace if worn). Re-assembler and tighten
carefully (figures 15a-15b).
Close the Condensate drainage cock.
Insert the Rilsan hose correctly inside the
pressure switch (fig. 16).
Decrease the demand of compressed air.
Change gaskets.
Clean/replace the suction filter
(figures 11a-11b).
Check belt tension (fig. 14).
PRO A29B-0 50 CM3_Zero
Nm
Max. torque
11
27
55
93
148
EVERY 100
EVERY 300
HOURS
HOURS
REMEDY