(2) The length of suspension bolts must be appropriate for a
distance between the bottom of the bolt and the bottom
of the unit of more than 18 mm as shown in Fig. 3-88.
(3) Thread the 3 hexagonal nuts and 2 washers (field
supply) onto each of the 4 suspension bolts as shown in
Fig. 3-89. Use 1 nut and 1 washer for the upper side, and
2 nuts and 1 washer for the lower side, so that the unit
will not fall off the suspension lugs.
(4) Adjust so that the distance between the unit and the
ceiling bottom is 12 to 17 mm. Tighten the nuts on the
upper side and lower side of the suspension lug.
(5) Remove the protective polyethylene used to protect the
fan parts during transport.
(6) Check with a tape measure or carpenter's level.
Nuts and washers
(use for upper and lower)
Double nut

3-35. How to Process Tubing

Refer to the section "5. HOW TO PROCESS TUBING".
Suspension bolt
Suspension lug
Notch
12 – 17 (mm)
Fig. 3-89