 Note:
Pressure regulator/relief
device must be supplied
by the customer on the
blanket gas port.
 Note:
A pressure switch
prevents system damage
by triggering an alarm
and stopping operation
of the unit if blanket
pressure drops below
recommended value.
 Note:
Field wiring used for
24VDC input must be
suitably rated.
Z10000 Natural Gas Odorization System

3. Installation

Installation should be performed by qualified
personnel in accordance with applicable state/
provincial and local codes and procedures.

3.1 Site Requirements

3.1.1 Unit Location

If possible install the Z10000 at or below the Odorant Storage
Vessel. This allows further reduction of blanket pressures on
the odorant storage tank.

3.1.2 Blanket Gas

Blanket pressure on the odorant tank provides the inlet
pressure head to the pump to help prevent cavitation
• 15–30 psig needed
• Nitrogen or pipeline gas

3.1.3 Electrical Power

• Typical: 24 VDC, 1.127 Amps
• Maximum: 24 VDC, 5.2 Amps

3.2 Equipment and Tools

Tools needed for installation of the Z10000 include:
• Hydraulic Pump Bleed Kit (Sentry P/N 6-05488Q)
• Tube Fitting Tools
• Electrical Wiring Tools

3.3 Tubing

Once an appropriate location has been determined for the
Z10000 and the unit has been properly mounted, install the
tubing per your company's procedures and applicable code.

3.4 Wiring

Always disconnect power before
servicing connections.
Use the guidelines below to wire any necessary connections.
Please note that not every connection described in this section
is used for every site. If you have any questions, please contact
Sentry Equipment Corp.

3.4.1 Electrical Connections

1. With power off, open the enclosure and open the
electronic access door.
2. Connect +24 VDC to TB-1, Terminal 1.