INSTALLATION
Install the tube so that it is horizontal.
放置挡水条,需确保挡水条放置水平。
Install side leaf glass and side leaf upper beam.
安装侧扇固玻和侧扇上横梁。
Install the protective seal of the two sides of the fixed glass and the fixed glass, and install
the beam:
1. Place the protective seal of the fixed glass first.
2. Install the fixed glass.
3. Install the beam downwards, and then lock it by the screws.
安装两侧固玻保护胶条和固玻,安装上横梁:
1. 先放置固玻保护胶条;
2. 安装固玻;
3. 自上而下安装上横梁,再锁上螺丝。
1463411-T01-A
0mm
IMPORTANT:
Tray MUST be level
along front edge.
重要:
底盘必须水平。
Note: Check whether the lower beam of
the side leaf has been pre-installed on
the side fixed glass.
注意:检查侧扇下横梁是否已预装在侧
固玻上。
Note: There are four M4 thread holes with
each side being locked by one screw.
注意:四个 M4 牙孔,每边能各能锁一个
螺丝即可。
安装
Install the vertical member of the side leaf which must be vertical to the floor and installed
in the middle together with the seal.
安装侧扇竖材,侧扇竖材需保持与地面垂直,且与挡水条居中安装。
The wall jamb
must be kept
vertical.
上墙材必须垂直。
6mm
STEP
1
Install the front upper-wall profile and the front lower beam with the former vertical to the
floor and 20mm from the external edge (stone base surface width is 80mm).
安装正面上墙材和正面下横梁,上墙材需保持与地面垂直,且内偏 20mm 安装(石基面宽
80mm) 。
0mm
6mm
STEP
3
Install the magnetic strip of the center pillar and the center pillar:
1. Insert the magnetic strip into the profile downwards.
2. Pat the whole profile into the fixed glass.
3. Check to confirm the distance from both sides to the fixed glass is about 663mm (the door
glass width is 650mm).
4. Lock by the fixing screws on the top of the center pillar.
安装中立柱磁条和中立柱 :
1. 先将磁条自上而下插入型材;
2. 再将型材整体拍入侧扇固玻;
3. 检查两侧到固玻间距为 663mm 左右(门玻宽度 650mm) ;
4. 锁上中立柱顶部固定螺丝。
STEP
5
-3-
0mm
Note: Both the vertical member of
the side leaf and the seal are
installed in the middle.
注意:侧扇竖材与挡水条居中安装。
0mm
6mm
STEP
2
STEP
4
STEP
6

Advertisement