7 Commissioning
7.5

Configuring the system

7.6

Final instructions

Fig.47
People
52
7.5.1

System draining

If at any time after installation it is necessary to drain and refill the central
heating system (e.g. when replacing a radiator) the De-Aeration function
must be activated to avoid air being trapped in the system.
See
De-Aeration function, page 48.
Once De-Aeration is complete recommission the boiler and check that the
inhibitor concentration is sufficient.
7.6.1

Handover

1. Carefully read and complete all sections of the Benchmark Commis­
sioning Checklist at the rear of this publication that are relevant to
the boiler and installation. These details will be required in the event
of any warranty work.
Important
The warranty will be invalidated if the Benchmark section is in­
complete.
2. The publication must be handed to the user for safe keeping and
each subsequent regular service visit recorded.
PN-0000333
3. Hand over the User's Operating, Installation and Servicing Instruc­
tions, giving advice on the necessity of regular servicing.
4. For IE, it is necessary to complete a "Declaration of Conformity" to
indicate compliance with I.S. 813. An example of this is given in I.S.
813 "Domestic Gas Installations" . This is in addition to the Bench­
mark Commissioning Checklist.
5. Set the central heating and hot water temperatures to the require­
ments of the user. Instruct the user in the operation of the boiler and
system.
6. Instruct the user in the operation of the boiler controls.
7. Demonstrate to the user the action required if a gas leak occurs or is
suspected. Show them how to turn off the gas supply at the meter
control, and advise them not to operate electric light or power
switched, and to ventilate the property.
8. Show the user the location of the system control isolation switch,
and demonstrate its operation.
9. Advise the user that they may observe a plume of vapour from the
flue terminal, and that it is part of the normal operation of the boiler.