4.2.1 Site preparation

Ensure that the site selected for the installation has the following:
-
Access to AC input power of 120 VAC.
-
Access to a natural gas line at a minimum gas line pressure of 3.5 inch W.C. to a maximum of 14 W.C.
-
Vent lengths as per Page 27
-
Combustion air and dilution are as per local codes.
-
Access for a drain for the condensation. See section 4.7
-
All gas piping, water piping and electrical conduit or cable must be arranged in a manner that does not interfere
with the removals of any panels or limit the access to service or maintenance of the unit.
-
For multiple boiler installations, it is critical to plan the positioning of each unit in advance. Adequate space must
be allowed for pre connections, and future service and maintenance requirements. All piping must include ample
provisions for thermal expansion.
-
If lead lag confirmations is to be utilized, it is important to identify the lead boiler and place this boiler in the area
that allows the control to be easy access for both operator and service personnel.
-
The water quality is crucial to the performance and longevity of this boiler. Ensure water quality is to the specifications
outlined in the water quality manual or warranty will be voided. Contact factory for further clarification if needed
WARNING
Always keep the area free and clear of all combustible materials and flammable vapors or liquids'. Ensure there are
no flammable items stored in the vicinity of the boiler.

4.2.2 Hoisting the boiler

The boiler is designed to be hoist if required using two 1 inch diameter rods, 48 inches long that can be placed through
the frame on either side of the fork lift slots. Ensure the lifting bars are properly placed through these holes and a sling
is used that has a minimum rating of 6000 lbs per sling. One sling must be used on each bar. Ensure no personnel
stands underneath the boiler as it is hoisted.
Lifting bar locations
Absolute Boilers 750-900-1050