COMMISSIONING
FIRST IGNITION OPERATION
Date
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installer
. . . . . . . . . . . . . . . . . . . . . . . . . .
1. Check the electrical supply.
Complete
. . . . . . . . . . . . . . . . . . .
4. Measure the gas inlet
standing pressure
Complete
..........................................................................................
7. Check the hydraulic water
tightness.
Complete
. . . . . . . . . . . . . . . . . . .
10. Measure the gas inlet
working pressure.
Complete
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
13. Explain to the end user
how to use the boiler/
timer/control
Complete
..........................................................................................
28
/
2. Check the type of gas and
change the gas if necessary.
Complete
. . . . . . . . . . . . . . . . . . .
5. Check the Flue
Complete
. . . . . . . . . . . . . . . . . . .
8. Set the heating power.
Complete
. . . . . . . . . . . . . . . . . . .
11. Check the boiler
combustion.
Complete
. . . . . . . . . . . . . . . . . . .
14.Complete the Benchmark
Log Book
Complete
. . . . . . . . . . . . . . . . . . .
3. Check the gas tightness.
Complete
. . . . . . . . . . . . . . . . . . .
6. Fill the installation.
Complete
. . . . . . . . . . . . . . . . . . .
9. Balance the central heating
circuit.
Complete
. . . . . . . . . . . . . . . . . . .
12. Gas rate the appliance.
Complete
. . . . . . . . . . . . . . . . . . .