Mueller CP2-10 Installation And Operation Manual
Mueller CP2-10 Installation And Operation Manual

Mueller CP2-10 Installation And Operation Manual

Compact chiller
Hide thumbs Also See for CP2-10:
Table of Contents

Advertisement

Quick Links

Compact Chiller
Models CP2-10 and CP2-20
INSTALLATION AND OPERATION MANUAL
Original English Version
Part No. 8826880
Effective December 21, 2011
Revised June 7, 2023

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the CP2-10 and is the answer not in the manual?

Questions and answers

Summary of Contents for Mueller CP2-10

  • Page 1 Compact Chiller Models CP2-10 and CP2-20 INSTALLATION AND OPERATION MANUAL Original English Version Part No. 8826880 Effective December 21, 2011 Revised June 7, 2023...
  • Page 3: Table Of Contents

    Condensing Unit Installation....................9 Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No.
  • Page 4 Instructions for Mounting the Multi-Stage Chiller Control Enclosure ..........15 Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No.
  • Page 5 Metal Components......................25 Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No.
  • Page 6 ............... . . 34 Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No.
  • Page 7: Section 1.0 - Introduction

    Section 1.0 – Introduction GENERAL INFORMATION Mueller® CP2-10 and CP2-20 compact chillers are designed to provide the efficient production of a chilled liquid cooling solution while requiring minimal installation time and maintenance. TECHNICAL SUPPORT This manual provides the basic installation and operating information for Mueller CP2-10 and CP2-20 compact chillers.
  • Page 8: Section 2.0 - Description Of The Equipment

    Mueller Accu-Therm® Mueller Milk Cooler Mueller E-Star HiPerForm “HPF/ESE” condensing units for chiller. Cold chiller water to the Mueller Accu-Therm plate cooler. Return water to the Mueller compact chiller. Warm milk to be cooled. Cooled milk to the Mueller milk cooler storage tank.
  • Page 9 138 cm 54 in CP2-10 352 kg 775 lb Approximate Weight CP2-20 383 kg 845 lb 54" 31" 52" Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880 Revised June 7, 2023...
  • Page 10: Refrigeration Components

    REFRIGERATION COMPONENTS Mueller CP2 compact chillers are designed to operate with two Mueller 5-horsepower E-Star HiPerForm “HPF/ ESE” condensing units for maximum performance and efficiency. Refer to the E-Star HiPerForm “HPF/ESE” condensing unit manuals for technical information. EVAPORATOR The Mueller compact chiller uses two totally enclosed, heavy-duty, stainless steel evaporators to provide years of trouble-free operation when properly installed and controlled.
  • Page 11: Electrical Components

    ELECTRICAL COMPONENTS The Mueller compact chiller has a complete electrical control system. The electronic temperature control is housed in a separate enclosure. The multi-stage chiller control must be mounted and wired to the flow switches, condensing units, temperature sensors, and pump. All wiring must be performed in accordance with the regulatory agency for the installation locality.
  • Page 12: Section 3.0 - Installation

    Section 3.0 – Installation INSPECTION Because it is possible for equipment damage to occur during shipment, Paul Mueller Company requires inspecting all equipment before unloading it from the freight truck. Carefully inspect the equipment for hidden damage. It may be difficult to collect for damage if it is not found prior to unloading. It is important to note any damage on the bill of lading and have the driver sign it.
  • Page 13 FIGURE 4: FORK LIFT CRATED FIGURE 5: SKID REMOVAL Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880 Revised June 7, 2023...
  • Page 14: Location

    • Efficiency: Locate the chiller as close as possible to the Mueller Accu-Therm plate cooler. This will improve efficiency by reducing heat gain and flow restrictions in the chilled liquid solution piping. CHILLED SOLUTION PIPING The piping between the compact chiller and the Accu-Therm plate cooler should be a minimum of 3-inch Schedule-40 or -80 PVC, stainless steel, or copper pipe.
  • Page 15: Condensing Unit Installation

    IMPORTANT: The circulation of controlled warm water or a completely drained evaporator is mandatory during pump-down or refrigerant recovery to eliminate evaporator damage due to freezing. Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880...
  • Page 16: Section 4.0 - Cleaning The System

    IMPORTANT: Never use chlorine as a bacteria inhibitor or cleaning agent as it will cause premature failure of the evaporator and plates within the remote, secondary plate cooler. A food-grade inhibitor, methylparaben, Part No. 9841027, is available from Paul Mueller Company. The water quality must meet the following standards: •...
  • Page 17: Liquid Solution For Instant Cooling

    IMPORTANT: A refractometer designed for testing the freeze point of propylene glycol solutions should be used to determine the actual freeze point of the solution. Please contact Paul Mueller Company’s Service Department for assistance in locating a supplier of propylene glycol refractometers.
  • Page 18: Section 5.0 - Evacuation, Charging, And Startup Of System

    NOTE: Energize crankcase heaters and allow a minimum of four hours of operation before a compressor startup. Ensure all service valves are open to avoid over-pressurization of system components. Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No.
  • Page 19: High-Pressure Control

    If the known product temperature does not correspond with the temperature display, the temperature control will require a calibration correction. Refer to Section 9 for sensor calibration. Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880...
  • Page 20: Section 6.0 - Equipment Sound Level

    Measurements were performed by a third party. SOUND MEASUREMENT Maximum recorded noise levels for this machine were recorded at less than 70 dB(A). Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880...
  • Page 21: Section 7.0 - Multi-Stage Chiller Control Installation

    ELECTRICAL REQUIREMENTS The Mueller multi-stage chiller control requires a 208 V/240 V/277 V power supply, fused at 20 amps maximum, or a 380 V/480 V power supply, fused at 10 amps maximum. A lockable disconnect is provided in accordance with CE Standard EN60947-3.
  • Page 22: Section 8.0 - Multi-Stage Chiller Control Electrical Wiring

    When sensors are installed in pipes discharging into a reservoir, Mueller recommends the sensors be installed in the six o’clock position. Care must be taken to never deform the sensor housing as damage to the enclosed circuit board could result. Mueller does not recommend the use of copper compression fittings on the digital temperature sensor.
  • Page 23: Field Wiring

    FIELD WIRING The Mueller multi-stage chiller control may be wired to provide 24-VAC output, dry switch closures, or any combination of the two. Please refer to the following diagrams for wiring procedures. FIGURE 7: SENSOR/REMOTE START/FLOW SWITCH WIRING SCHEMATIC Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No.
  • Page 24 For installations requiring 24-VAC output, the 24-VAC signal is available by connecting to the bottom two terminals, C and D. N (Constant) L (Switched) Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880 Revised June 7, 2023...
  • Page 25: Flow Switch And Remote Switch Wiring

    FLOW SWITCH AND REMOTE SWITCH WIRING The Mueller multi-stage chiller control is designed for operation with a normally open (NO) flow switch and a remote switch. The NO flow switch is an optional programmable feature, although installation is highly recommended (see Section 9.2 for flow switch programming).
  • Page 26: Section 9.0 - Multi-Stage Chiller Control Programming

    Section 9.0 – Multi-Stage Chiller Control Programming PROGRAMMING OVERVIEW The Mueller multi-stage chiller control is field programmable to allow for installation on most chiller systems utilizing one to ten independent stages. Each stage has a programmable setpoint temperature, differential, operation mode, and anti-short cycle feature; as well as being able to monitor one of two system temperatures.
  • Page 27: Programming Parameters Chart

    Energizes on temperature decrease. 0 Min. Anti-Short Cycle (ASC) Parameter Code: Sensor A, chilled water supply. Sensor B, chilled water return. Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880 Revised June 7, 2023...
  • Page 28: Section 10.0 - Multi-Stage Chiller Control Operation

    Once this delay expires, any breaking of the flow switch for longer than one second will cause the alarm light on the front panel to light and the alarm output relay to close as well as all Cool mode stages to open. Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No.
  • Page 29: Alarm Features

    NOTE: There is a four-second delay when the pump is energized or de-energized before flow switch monitoring is active to allow the flow of chilled solution to close the switch or open the switch. Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No.
  • Page 30: Section 11.0 - Chiller Maintenance

    Section 11.0 – Chiller Maintenance 11.1 GENERAL The Mueller CP2 compact chiller requires minimal maintenance. It is recommended that a knowledgeable service technician perform the following scheduled maintenance procedures on an annual basis: Check the glycol level to ensure adequate chilled water solution levels.
  • Page 31: Section 12.0 - Disposal

    Section 12.0 – Disposal 12.1 GENERAL If the Mueller CP2 compact chiller is removed for resale or disposal, ensure the materials, refrigerant, and oils are handled and/or disposed of according to applicable codes and regulations. 12.2 REFRIGERANT The Mueller CP2 compact chiller contains R-507 hydrofluorocarbon, which has zero ozone depletion potential.
  • Page 32: Section 13.0 - Safety

    Technicians handling refrigerants should wear side-shielded safety glasses, impervious (preferably butyl-lined) gloves, and other protective equipment or clothing as required by the situation. Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880...
  • Page 33: Section 14.0 - Equipment Markings

    14.3 LABEL NO. 8829047, CE UKCA DATA TAG 14.4 LABEL NO. 8829330, WARNING SYMBOL: BURN HAZARD, HOT SURFACE Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880 Revised June 7, 2023...
  • Page 34: Label No. 8829324, Warning Symbol: Arc Flash

    LABEL NO. 8826916, LIFT POINT 14.10 LABEL NO. 9901403, WATER/SOLUTION IN 2009 9901403 14.11 LABEL NO. 9901404, CHILLER WATER/SOLUTION OUT 2109 9901404 Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880 Revised June 7, 2023...
  • Page 35: Label No. 8829326, Read Operator Manual

    14.12 LABEL NO. 8829326, READ OPERATOR MANUAL 14.13 LABEL NO. 8829325, LOCKOUT Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880 Revised June 7, 2023...
  • Page 36: Section 15.0 - Manual Parameters Selection

    1.0 to 9.5°F (0.4 to 5.4°C) Sensor Select “A” or “b” Mode Select “H” or “C” Anti-Short Cycle “0” to “10” Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880 Revised June 7, 2023...
  • Page 37 “y” or “n” 14 Temperature Degrees F/C “f” or “c” Software Software “_ _ _”* *Displays installed software version. Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880 Revised June 7, 2023...
  • Page 38: Declaration Of Conformity

    Printed Name: Kevin Bartholomaus Position Held: Technical Services Manager Signature of Manufacturer: ORIGINAL DECLARATION 16.2 DECLARATION OF INCORPORATION Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880 Revised June 7, 2023...
  • Page 39: Section 17.0 - Wiring Schematic (Attached)

    Section 17.0 – Wiring Schematic (Attached) Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880 Revised June 7, 2023...
  • Page 41 (INSTALL JUMPER IF NOT USING) CONNECT INSIDE REFRIG. CONTACT REFRIG. CONTACT CONTROL BOX N.O. FLOW SWITCH #1 N.O. FLOW SWITCH #2 Mueller Compact Chiller, Models CP2-10 and CP2-20 Effective December 21, 2011 Installation and Operation Manual, Part No. 8826880 Revised June 7, 2023...
  • Page 43 Noordgang 14 | 7141 JP Groenlo | The Netherlands Service Telephone: +31 (0) 88 683 0010 | technicalsupport@paulmueller.com +31 (0) 88 683 0000 | WWW.PAULMUELLER.COM ©2023 Paul Mueller Company | 23-2306010832p-DFESGF | 8826880...