Connecting - Siemens SITRANS LG260 Operating Instructions Manual

Guided wave radar
Hide thumbs Also See for SITRANS LG260:
Table of Contents

Advertisement

Connection technology
Connection procedure
18
In systems with potential equalisation, connect the cable screening
directly to ground potential at the power supply unit, in the connection
box and at the sensor. The screen in the sensor must be connected
directly to the internal ground terminal. The ground terminal outside
on the housing must be connected to the potential equalisation (low
impedance).
5.2

Connecting

The voltage supply and signal output are connected via the spring-
loaded terminals in the housing.
Connection to the display and adjustment module or to the interface
adapter is carried out via contact pins in the housing.
Information:
The terminal block is pluggable and can be removed from the
electronics. To do this, lift the terminal block with a small screwdriver
and pull it out. When reinserting the terminal block, you should hear it
snap in.
Proceed as follows:
1. Unscrew the housing lid
2. If a display and adjustment module is installed, remove it by turn-
ing it slightly to the left
3. Loosen compression nut of the cable gland and remove blind
plug
4. Remove approx. 10 cm (4 in) of the cable mantle, strip approx.
1 cm (0.4 in) of insulation from the ends of the individual wires
5. Insert the cable into the sensor through the cable entry
Fig. 9: Connection steps 5 and 6
1
Single chamber housing
2
Double chamber housing
6. Insert the wire ends into the terminals according to the wiring plan
Note:
Solid cores as well as flexible cores with wire end sleeves are insert-
ed directly into the terminal openings. In case of flexible cores without
end sleeves, press the terminal from above with a small screwdriver,
the terminal opening is then free. When the screwdriver is released,
the terminal closes again.
SITRANS LG260 - Operating Instructions
1
2
PBD-51041061

Advertisement

Table of Contents
loading

Table of Contents