Before putting into operation, the entire system should be flushed through. Particles in the system compromise the
operating reliability.
Fill the heating system slowly with water and vent all the air.
Open the cold water stop valve and all hot water nozzles. The hot water heat exchanger is full when water leaks out
of all hot water nozzles. Then close all nozzles again.
Start-up the heating system.
Set the DHW temperature and supervise the system while heating up.
While the System is heating up, water will leak out of the safety valve.
Before the handover of the system to the end user/owner, the plumbing contractor should ensure that the
system is tested to full load, controls are set and that pipe work and connections are without leaks. Afterwards,
the end user has to be instructed in the operation and handling of the tank, as well as the system. The instruction must
to be documented in the installation and maintenance record.,
Please note that the operation and lifetime of the system depend decisively on a regular maintenance.

7 Maintenance and wear parts

Regular maintenance increases the lifetime and operation reliability of the system. Decalcification at regular intervals may be
necessary in highly calcareous water areas.
1 .
Close the cold water stop valve and drain the tank to check the inner tank as well as the heat exchanger. Disconnect any
electrical devices from the appliance. Then, carefully remove the insulation of the flange cover and unscrew the flange
cover. Limescale and rough residues can be crushed by a wooden bar. Only use an approved decalcifier. Screw the
flange cover hermetically after the cleaning process by using a new flange seal. Fill the tank and check all connections for
tightness. Finally, replace the insulation and, if necessary, remount the electrical devices accordingly.
A chemical decalcification can be carried out by a specialist using an approved decalcifier and taking the appropriate
precautions. Please note that the tank must be disconnected from the DHW installation (cold water / hot water /
circulation).
2.
For protection purposes, the tank is equipped with a magnesium protection anode. Its transmission depends on the local
water properties. It should be examined for the first time after 2 years and afterwards annually in order to check its
transmission. The diameter should be at least 1/3 of the original diameter, the surface should be homogenous and
without any limescale crust. If necessary, it should be replaced by an original Wikora anode to protect the tank against
corrosion.
2.a. Alternatively, the tanks can be equipped with an external current anode. Please note that a protection against
corrosion is only guaranteed if the anode is energized and connected accordingly.
If the protection anode is neglected, this can cause damage through corrosion and lead to a loss of warranty.
3.
The safety valve protects the tank against excess pressure. The functional capacity must be checked at regular intervals
by venting. If an expansion vessel is used, the safety valve is not, or only rarely, required. Over a longer period of time
therefore, it can become blocked and not function when needed.
4.
If there is a danger of freezing, the DHW tank should be permanently heated or completely emptied.
5.
A damp cloth is sufficient to clean the outer parts. Please avoid using any abrasive or solvent cleaning agents.

8 Recycling and disposal

The products are specified and manufactured according to VDI 2243. The products are mechanically separable and 100%
recyclable. Make sure that the components are disposed according to the relevant regulations.
© Wikora GmbH
Page 6
As of 1/31/2019
Errors excepted.

Advertisement

Table of Contents
loading

This manual is also suitable for:

Wbo 505 duoWbo 505 h50Wbo 505 h60Wbo 505 wpsol

Table of Contents