Use the following steps to install a Trillium Compact in the Carrying Case / Insulating Cover for
insulating purposes at the installation site:
1. Prepare a flat installation surface.
2. Secure the cable to the side of the seismometer with a tie wrap (see
3. Use tape or a heavy object to strain relieve the cable on the installation surface.
4. Use your preferred method of aligning and leveling the seismometer (see
Leveling a Trillium Compact in a Vault Installation" on
If you are burying the Trillium Compact and its insulating cover, pull all of the foam out
of the cover. Retain these pieces of foam for future installations and transport. See
"Alignment, Leveling, and Placement Features" on page 36
buried installations.
Figure 3-4 - Cut-away illustration of a Trillium Compact in the insulating cover
The seismometer in Figure 3-4 illustrates model numbers TC120-SV1 and TC20-SV1.
16889R10 • 2020-11-12
Chapter 3 - Installing a Trillium Compact Vault Seismometer
page 39).
Figure 3-4
below).
"Aligning and
for more information on
Page 44