Teeth Of The Drive; Safety Check; Functional Test; Checks Before Initial Start-Up - HADEF EHH Installation, Operating And Maintenance Instructions For The Installer And The User

Single girder manual overhead travelling crane
Table of Contents

Advertisement

NOTICE!
Hoists up to 1000 kg capacity and without motor-driven trolleys of hoisting unit must be tested by a "qualified
person" before putting into operation for the first time.
Hoists of 1000 kg capacity and up or with more than one motor-driven hoist movement; i.e. lifting and trolley
movement, must be tested by a "licensed qualified person" before putting in operation.
An exception is "hoists ready for operation" acc. validated national regulations with EU-declaration of
conformity.
Definition "qualified person" (former expert)
A "qualified person" has learned, due to occupational training and experience and the job that the person has
done, the skills needed to tests the material for one's work.
Definition "licensed qualified person" (former approved expert)
A "licensed qualified person" has, due through special occupational training, knowledge about testing of the
material for one's work and knows the national accident prevention regulations and other prescriptions and
technical regulations. This person must test the material for one's work regularly with regard to design and
kind of use. The license will be given to qualified person be the approved supervision authorities (ZÜS).
Pos: 12.2.2.1 /1_HADEF/9--INBETRIEBNAHME/Allgemein/Getriebe/05.Krane - Verzahnung Antrieb @ 2\mod_1289228080444_52.docx @ 16658 @ @ 1
8.2

Teeth of the drive

The teeth of the drive must be lubricated before putting the equipment into operation.
Pos: 13.1 /1_HADEF/10-SICHERHEITSPRÜFUNG/*Ü1*/#. Kapitel - Sicherheitsprüfung @ 0\mod_1172647514342_52.docx @ 401 @ @ 1
9

Safety check

Pos: 13.2 /1_HADEF/10-SICHERHEITSPRÜFUNG/Allgemein/01.Sicherheitsprüfung Alle @ 0\mod_1178197796463_52.docx @ 5700 @ @ 1
Before putting into service initially or when putting back into service, it must be checked whether:
All fastening screws (if existent), socket pins, flap socket and safety devices are tightened and secured.
Pos: 14.1 /1_HADEF/11-FUNKTIONSPRÜFUNG/*Ü1*/#. Kapitel - Funktiosprüfung @ 0\mod_1176446880639_52.docx @ 4028 @ @ 1
10

Functional test

Pos: 14.2.1 /1_HADEF/11-FUNKTIONSPRÜFUNG/Funktionsprüfung/Krane - Alle @ 2\mod_1287562125698_52.docx @ 16463 @ @ 1
10.1

Checks before initial start-up

Design
Check all screws and safety connections
The open-lying teeth of the crane trolley must be lubricated.
10.2
Functional test
Function - crane trolley
Check properly running of the crane.
Check the beam for obstacle-free running.
Carefully move the crane to the end positions and check the positions of the end stops.
Pos: 15.1 /1_HADEF/12-INSTANDSETZUNG/*Ü1*/#. Kapitel - Instandhaltung @ 0\mod_1172647603139_52.docx @ 405 @ @ 1
11
Maintenance
Pos: 15.2.1 /1_HADEF/12-INSTANDSETZUNG/Allgemein/01.Allgemein @ 0\mod_1173251926256_52.docx @ 469 @ @ 1
11.1
General
All monitoring, servicing and maintenance operations are to ensure correct functioning of the equipment;
they must be effected with utmost care.
Only "qualified persons" may do this work.
Servicing and maintenance work must only be done when the hoist is not loaded.
Records must be kept of all test results and measures taken.
Pos: 15.2.2 /1_HADEF/12-INSTANDSETZUNG/Allgemein/02.Überwachung @ 0\mod_1173254503420_52.docx @ 472 @ @ 1
11.2
Monitoring
The monitoring and servicing intervals stated are valid for operation under normal conditions and single-shift
operation. In case of severe operating conditions (e.g. frequent operation with full load) or special
environmental conditions (e.g., heat, dust, etc.), the intervals must be shortened correspondingly