Check Track Sag --- every 50 hours
Swing the upperstructure 90 ° and lower the bucket to raise
the track off the ground as shown.
Keep the angle between the boom and arm 90 to 110 ° and
position the bucket's round side on the ground. Place blocks
under the machine frame to support the machine.
Rotate the raised track in reverse two full rotations and then
forward two full rotations.
Measure distance (A) at the middle of the track frame from
the bottom of the track frame to the back face of the track
shoe.
Track sag specifications
Model
ZX135US-6
ZX225USLC-6
ZX345USLC-6
f
NOTE: Check track sag after thoroughly removing soil stuck
on the track area by washing.
Adjust Track Sag
Precautions for Adjusting Track Sag
1. If track sag is not within specifications, loosen or tighten
the track following the procedures shown on the next
page.
2. When adjusting track sag, lower the bucket to the
ground to raise one track off the ground. Repeat this
procedure to raise the other track. Each time, be sure to
place blocks under the machine frame to support the
machine.
3. After adjusting track sag of both tracks, move the
machine back and forth several times.
4. Check track sag again. If track sag is not within
specifications, repeat adjustment until correct sag is
obtained.
OPTIONAL ATTACHMENTS AND DEVICES
PAD CRAWLER SHOE
A
250 to 280 mm
300 to 335 mm
340 to 380 mm
13-4
M104-07-067
M107-07-068

Advertisement

Table of Contents
loading

This manual is also suitable for:

Zaxis 225us-6 classZaxis 345us-6 classZaxis 135us-6Zaxis 225uslc-6Zaxis 345uslc-6

Table of Contents