HRV2000i and HRV2000e Start-up Form and Checklist
Complete this form for each unit and email, fax or mail to Venmar CES immediately after start-up to validate warranty
and to provide valuable information for personnel performing future maintenance or for factory assistance to address
below.
Read the Installation, Operation and Maintenance Instructions Manual before proceeding.
Leave a copy of this report with the Owner and at the unit for future reference and permanent record.
To ensure proper operation of each unit qualified personnel should perform the start-up, complete the checklist and
report.
All units are factory run tested. Blowers are set up to run correct when power is connected. If any blower is running
backwards disconnect power and switch two leads (on three-phase power) to ensure proper rotation.
Venmar CES
1502 D Quebec Avenue
Saskatoon, Saskatchewan
Canada S7K 1V7
Phone: 1-866-4-VENMAR (1-866-483-6627)
Fax: (306) 651-6009
Table K1: Pre Start-up Checklist
Checklist Item
1
Is the electrical disconnect set to the 'Off' position?
2
Have shipped loose parts, obstructive packaging, objects, tie downs on fans been removed?
3
Are fans and motors rotating freely?
4
Are fan wheels and drive set screws tight?
5
Are belt alignment and tension correct?
Are air filters installed, clean or replaced? If filters are equipped with optional differential pressure switch, check
6
desired setpoint does not exceed factory setting of 0.8" w.c. [200 Pa].
7
Are damper and linkages free of movement?
8
Is ductwork connected and complete?
9
Are condensate drain connections trapped, installed correctly and filled?
10 Are all shipped loose or field supplied components correctly installed and wired?
11 Has power supply and control wiring been inspected and approved by the Local Authorities?
12 Have factory and field wiring connections been checked and tightened?
13 Are all fuses properly installed in holders?
Is voltage at the disconnect switch within 10% of nameplate and phase-to-phase readings within 2% of
14
nameplate?
15 Are field piping and venting installation and connections for heating and cooling options completed and tested?
16 Have all thermostat setpoints been checked and adjusted?
VCES-HRV-SF-2 – HRV2000i/e Start-up Form
IMPORTANT

Unit Identification Information

Project: __________________________________________
Model Number: ___________________________________
Serial Number: ____________________________________
Tag: _____________________________________________
Jobsite Contact: ___________________________________
Job Name:________________________________________
Job Address: ______________________________________
Telephone: _______________________________________
Email: ___________________________________________
Yes
N/A
June 2014

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the HRV2000i and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Venmar HRV2000i

  • Page 1 HRV2000i and HRV2000e Start-up Form and Checklist IMPORTANT • Complete this form for each unit and email, fax or mail to Venmar CES immediately after start-up to validate warranty and to provide valuable information for personnel performing future maintenance or for factory assistance to address below.
  • Page 2 Check the setpoints on thermostats and controls; adjust and record changes as required. When unit has achieved steady state take measurements and complete readings section of start-up form for each operating cycle to verify all components are functioning properly. VCES-HRV-SF-2 – HRV2000i/e Start-up Form June 2014...
  • Page 3 Company Name: __________________________________ set screws and terminals. Tighten where required. Telephone: _______________________________________ Additional Comments: Email to Tech Support (venmarservice@venmarces.com) or fax to 306-244-4221. _________________________________________________ _________________________________________________ _________________________________________ VCES-HRV-SF-2 – HRV2000i/e Start-up Form June 2014...