Assembly and installation
Installation and acceptance procedures
Procedure 2-2 (continued)
Remote site RPE group installation
.
Install 5/12-V converter circuit pack in RPE shelf. Refer to Figure 2-8
1 2
and to Procedure 2-3.
.
At the QBL14 install fuses for RPE shelf and set shelf power switch to
1 3
ON. Refer to Figure 2-4.
.
1 4
Unpack, inspect and insert circuit packs into the RPE shelf as
directed by the service order. Refer to Figure 2-8, Procedure 2-3 and
service order.
1 5 . Add related office data. Refer to Data Administration Implementation
herein, service order and Figure 2-10.