Tools / 安装工具
Phillips/Flat-head
Adjustable wrench
Socket wrench
screwdriver
套筒扳手
活动扳手
十字 / 一字螺丝刀
Wire stripper
COAX crimping tool
Hydraulic pliers
剥线钳
液压钳
压线钳
Measuring tape
Protective gloves
Insulated gloves
卷尺
防护手套
绝缘手套
Short-handle Phillips
Electroprobe
Step ladder (2 m)
Electrician's knife
screwdriver (85 mm)
电笔
人字梯(2m)
电工刀
短柄十字螺丝刀(85mm)
UPS PDC Layout / 结构示意图
NOTE / 说明
Cabinet dimensions (H x W x D): 2000 mm x 800 mm x 850 mm (2 PCS)
机柜尺寸(高×宽×深):2000mm×800mm×850mm (2pcs)
Input circuit
T7-3P
breaker
输入空开
TEST
QF
Surge protective
device (SPD) and
SPD circuit
breaker
FS QFS
T5-3P
防雷器及防雷空开
QF3
T7-4P
Maintenance
bypass circuit
TEST
breaker
维修旁路空开
QF1
PDF1
PDF2
NOTE / 说明
The positions and number of circuit breakers in the figure are for reference only. The actual product prevails.
空开位置和数量仅为示意,请以实物为准。
2
Installing an UPS PDC / 安装UPS配电柜
Checking Before Installation / 安装前检查
Open the packing case, and check that all components listed in the packing list are intact. Ensure that all components
are available before cleaning up the package materials. If components or fittings are damaged during transportation or
do not comply with the order contract, make records onsite and contact the local Huawei regional office or
representative office immediately.
Hammer drill
Claw hammer
打开包装箱,根据装箱清单检查设备的配件是否齐全、是否在运输过程中损坏。清除包装材料之前,要确保所有配件都
冲击钻
羊角锤
已找到。如设备和配件在运输中损坏或与订货合同不符,应及时做好现场记录,并与华为公司当地分公司或办事处代表
联系。
Installing a Single Cabinet / 安装机柜
Move the cabinet from the wood pallet to the ground.
将机柜从木栈板移动至地面。
Level
Plan the cabinet installation position based on the following figure.
Diagonal pliers
参考下图规划机柜安装位置。
斜口钳
水平尺
Unit: mm
单位:mm
Heat gun
热风枪
850
Drill holes using a hammer drill and install expansion bolts.
用冲击钻钻孔并安装膨胀螺栓。
Align the cabinet with mounting holes, and use a level to level the cabinet by adjusting the leveling feet.
将机柜对齐安装孔,配合水平尺调节地脚螺栓使机柜水平。
Insert bolts into the mounting holes and partially tighten the bolts.
将螺栓插入安装孔并预紧固。
T7-3P
Tighten the bolts in diagonal order.
按对角线顺序交叉紧固螺栓。
TEST
Installing Parallel Busbars / 安装并柜铜排
QF2
Output circuit
breakers
Install parallel bars, PE bars, and N bars.安装并柜铜排、PE排和N排。
输出空开
T5-3P
QF5 QF6
QF4
NOTE / 说明
If the cabinet is installed on a support,
skip steps 2 and 3.
如果机柜安装在支架上,步骤2、3可省略。
600
600
730
FRONT
FRONT
800
800
Bottom view of the UPS PDC / UPS配电柜底部视图
NOTE / 说明
1. Wrench a leveling foot clockwise to elevate the
cabinet, or wrench an anchor bolt counterclockwise to
lower the cabinet. The adjustable height ranges from
0 mm to 8 mm.
顺时针方向将机柜调高,逆时针方向调低。地脚调节
范围:0mm~8mm。
2. Adjust four leveling feet to avoid damage to the
cabinet. Adjusting only one leveling foot may slant the
cabinet.
机柜调平过程中,不要只调节一方地脚的高度,尽量
四方地脚协调调节,以免机柜倾斜造成机柜损坏。
Parallel bars: L1, L2, L3
并柜铜排:L1、L2、L3
N copper bar
N排
PE copper bar
PE排
3
Installing Cables / 安装线缆
Input cables / 输入接线
Maintenance bypass
维修旁路
Front view of the UPS PDC / UPS配电柜前视图
Output cables / 输出接线
Front view of the UPS PDC / UPS配电柜前视图
NOTE / 说明
The ground terminal is identified by a
sign.
接地端子通常以
标识。
4
NOTE / 说明
Cables are routed in and out from the top.
进出线方式:上进上出。