Greenheck ESJ-202 Installation, Operation And Maintenance Manual page 7

Stationary, non-drainable blade louvers

Advertisement

Multiple Section Wide x Single Section High Installation - Supported
Figure 4.1
Figure 4.2
Figure 4.3
Structural Reinforcing (by others)
®
1. Locate the optional extended sill, if provided, and
place in the opening.
2. Locate mounting angles and fasteners required to
attach the louver to the structure. Clip angles and
fasteners are by others unless the optional mounting
angles have been ordered from manufacturer with
the louvers. Anchors to the structure are by others
and are not manufacturer provided.
(Mounting Clip Details)
3. Place the left louver section (as viewed from the
exterior) in the opening and shim around the
perimeter to maintain proper spacing for backer rod
and caulk joint.
4. Using the appropriate fasteners, secure the
mounting angles to the back of the louver frame at
the perimeter.
5. Ensure the louvers is level and in the correct
location within the opening and secure the mounting
angles to the structure using the correct anchor (by
others) for the building substrate material.
6. Place the next louver section to the right of the
first louver section and repeat steps 3-5 above to
secure the louver to the structure. Follow the same
procedure for any additional sections to the right.
7. Install additional structural supports (not by
manufacturer) at the vertical louver mullions. Secure
the louver frame to the structural support with the
appropriate mounting angles and/or anchors (not by
manufacturer).
8. Once the louver assembly is secured to the
structure, install backer rod and caulk around the
perimeter of the opening at the front of the louver as
well as the mullion joint between the louver jambs.
Figure 4.4
Stationary, Non-Drainable Blade Louver Models
(Extended Sill Details)
7