General Louver Installation Instructions
Installation Instructions
1. Locate all crates, boxes, cartons, etc.
2. Use care when handling louver sections to prevent damage. Louvers are to be carefully lifted by the louver
frame or supports. Use multiple lifting points when possible to avoid deformation or distortion of louver
components. DO NOT LIFT LOUVERS BY THE LOUVER BLADES. Use appropriate caution to prevent
damage to the louver finish.
3. Remove louvers and any provided accessories from the packaging and inspect for damages. Verify louver
dimensions and that all required pieces are present.
4. Single section louvers will ship fully assembled. Multiple section assemblies will ship as individual louver
sections to be combined into the larger assembly at installation. Large multiple section louver assemblies may
ship in multiple crates.
5. All louver sections will have a factory applied louver label affixed. This label will identify the louver size and a Tag
identification if one was provided during the order process.
6. Verify that all required installation hardware is available, to include mounting angles and fasteners (customer
provided or optional manufacturer provided). Inspect the opening for any damage or issues that may affect
installation of the louvers. Remove any obstructions or debris as required. Adequate substrate depth must be
verified.
7. Check the dimensions of the opening to verify the louver will fit correctly. Check the opening is square and
plumb.