5 Installing the mounting system

Prior to installation, the module array must be measured out on the roof and the position of the modules
determined, taking into account any obstacles such as light domes or strips, fans or drains.
The individual mounting steps for the east/west system variation are explained below with reference to the
mounting variations (MV) for the different installation options or the system variations "south" and
"butterfly". This is then followed by the respective work sequence.

5.1 Substrate plate installation and support component mounting

Arrange substrate plates
Position and fasten module supports
Änderungen vorbehalten. Abbildungen sind beispielhaft und können vom Original abweichen.
V4.2.1 – März 2022/TP,
Copyright novotegra GmbH
Define starting point and measure up first whole
substrate plate. Lay the following substrate plates
(whole/half) according to planning documents
The substrate plate overlaps must always been
taken into account. The substrate plates must be
laid on top of an existing and suitable protection
fleece.
Position module supports (high/low) on the
substrate plates according to planning documents.
Fasten each support at the positions specified with
four 6 x 80 mm support mounting screws. The
supports must be placed in the corners of the
(whole) substrate plates. On these corners, the
substrate plates (half) may overlap.
The horizontal and vertical substrate plate line grid
pattern must be adhered to. Always refer to the
planning documents.