5.2 Rail mounting and fastening

Position green roof C-rail
Connect green roof C-rail
1
2
3
Änderungen vorbehalten. Abbildungen sind beispielhaft und können vom Original abweichen.
V4.2.1 – März 2022/TP,
Copyright novotegra GmbH
Place rail on module supports.
Fasten a 6.5 x 51 mm module support rail mounting
screw as close to the middle of each module
support as possible.
Do not over tighten the screws. Maximum rail
overhang on the last module support 65 cm. Always
heed the planning documents. Each rail part must
lie on and be fastened to at least two module
supports.
After the module support and rail installation, the
substrate is placed on top. The ballasting is
achieved with the substrate; refer to the planning
documents for the substrate weight per m². If
necessary, additional stones must be put on top of
the substrate plates as ballast. The mounting
system will only stand securely once the required
amount of ballast/substrate has been put in place.
Observe the accident prevention regulations when
sawing the rails.
Push the rail connector set (1) halfway into one of
the rails to be connected (2) and fasten it there with
one self-drilling screw on either side, at a distance
of approx. 20 mm to the end of the rail. After that,
push the other rail fully onto the rail connector set
until both rail ends meet (3), then fasten as
described above.
Do not over tighten the screws.
Observe the accident prevention regulations when
sawing the rails.
8