Testing Defrost Thermostat; Air Flow Measurement And Adjustment; Total External Static Pressure - Maytag Amana H Series Installation Instructions Manual

Self-contained package air conditioners and heat pump units, seer2 with r-410a
Table of Contents

Advertisement

NOTE: The PCBDM133 defrost controls are shipped
from the factory with the compressor delay option
selected. This will de-energize the compressor
contactor for 30 seconds on defrost initiation and
defrost termination. If the jumper is set to Normal,
the compressor will continue to run during defrost
initiation and defrost termination. The control will
also ignore the low-pressure switch connected to
R-PS1 and PS2 for 5 minutes upon defrost initiation
and 5 minutes after defrost termination.
To check the defrost control for proper sequencing,
proceed as follows: With power ON; unit not running.
1. Jumper defrost thermostat by placing a jumper wire
across the terminals "DFT" and "R"/" R-DFT" at
defrost control board.
2. Remove jumper from timer pins and jump across test
pins on defrost control board.
NOTE: Do not use screwdriver or field supplied
jumper to test the control.
3. Set thermostat to call for heating. System should go
into defrost within 21 seconds.
4. Immediately remove jumper from test pins.
5. Using VOM check for voltage across terminals "C &
O". Meter should read 24 volts.
6. Using VOM check for voltage across fan terminals
DF1 and DF2 on the board. Should read line voltage
(208-230 VAC) indicating the relay is open in the
defrost mode.
7. Using VOM check for voltage across "W"/"W2" & "C"
terminals on the board. Should read 24 volts.
8. If not as above, replace control board.
9. Set thermostat to off position and disconnect power.
Remove jumper from defrost thermostat and replace
timer jumper to the desired defrost time.
NOTE: Remove jumper across defrost thermostat
before returning system to service.
PCBDM133 Defrost Control

Testing Defrost Thermostat

1. Install a thermocouple type temperature test lead on
the tube adjacent to the defrost control. Insulate the
lead point of contact.
Figure 8
2. Check the temperature at which the control closes its
contacts by lowering the temperature of the control. It
should close at approximately 30°F.
3. Check the temperature at which the control opens its
contacts by raising the temperature of the control. It
should open at approximately 60°F.
4. If not as above, replace control.
AIR FLOW MEASUREMENT AND
ADJUSTMENT
After reviewing section on DUCTING, proceed with airflow
measurements and adjustments. Unit's blower curves
(in Specification Sheets) are based on external static
pressure (ESP, in. of W.C.). The duct openings on the unit
are considered internal static pressure, so as long as ESP
is maintained, the unit will deliver the proper air up to the
maximum static pressure listed for the CFM required by the
application (i.e. home, building, etc.).
In general 400 CFM per ton of cooling capacity is a rule
of thumb. Some applications depending on the sensible
and latent capacity requirements may need only 350
CFM or up to 425 CFM per ton. Check condition space
load requirements (from load calculations) and equipment
expanded ratings data to match CFM and capacity.
After unit is set and ducted, verify ESP with a 1" inclined
manometer with pitot tubes or a Magnahelic gauge
and confirm CFM to blower curves in the specification
sheets. All units have multiple speed blower motors. If
factory selected speed is not utilized, the speed tap can
be changed. Never run CFM below 350 CFM per ton,
evaporator freezing or poor unit performance is possible.

Total External Static Pressure

1. Using a digital manometer measure the static
pressure of the return duct at the inlet of the unit
(Negative Pressure).
Total External Static
2. Measure the static pressure of the supply duct
(Positive Pressure).
3. Add the two readings together.
11
.