Download Print this page

Emerson Rosemount 326 Quick Start Manual page 3

Hygienic process connection adapter

Advertisement

2 Install the weld-in adapter
Use the weld-in adapter to install transmitters with G1 process
connections to containers or pipes.
Prerequisites
After welding, allow the adapter to cool before installing. Do not weld
the adapter to the container or pipe with the transmitter connected.
Procedure
1. Bore a hole that has the outside diameter of the adapter in the
pipe or container wall.
Maximum oversize: 0.008 in (0.2 mm)
2. Weld the adapter.
Note
While welding, prevent the adapter from warping.
a) Turn the marking (1) (marking may vary) to the
position shown below for the display of the screwed
transmitter.