Honeywell 7800 Series Installation Instructions Manual page 20

100 vac relay modules
Hide thumbs Also See for 7800 Series:
Table of Contents

Advertisement

RM7890, RM7895 100 Vac
WARNING
Explosion Hazard.
Can cause severe injury, death or property damage.
Use extreme care while testing the system. Line voltage
is present on most terminal connections when power is
on.
1 . Open the master switch before removing or installing the
relay module.
2 . Make sure all manual fuel shutoff valve(s) are closed be-
fore starting the initial lightoff check and the Pilot Turn-
down tests.
3 . Do not put the system into service until you have satisfac-
torily completed all applicable tests in this section and any
others required by the equipment manufacturer.
CAUTION
Equipment Damage Hazard.
Use of improper equipment will cause operational
failure.
Do not replace the RM7890, RM7895 Relay Module with
a lower or higher functioning relay module until you
have made the necessary wiring changes or the burner
will not sequence.
IMPORTANT
1 .
If the system fails to function properly, refer to 7800
SERIES Relay Modules Checkout and Troubleshooting,
form 65-0229.
2 . Repeat all required CHECKOUT tests after all adjust-
ments are made. All tests must be satisfied with the
flame detector in its final position.
Equipment Recommended
Volt ohmmeter (one megohm/volt minimum sensitivity):
a . 0 to 300 Vac range.
b . 0 to 6000 ohms range.
c . 0 to 10 Vdc range.
Checkout Summary
1 . Preliminary inspection, all installations.
2 . Flame signal measurement, all installations.
Minimum Acceptable Steady dc Voltage
1.25 Vdc
a
This minimum or a stronger signal should be easily obtained if the detector is installed correctly and positioned to properly sense the flame.
This voltage must be obtained before completing checkout.
32-00216-01
3 . Initial lightoff check for proved pilot, all installations using
a pilot.
4 . Initial lightoff check for direct spark ignition (DSI) of oil, all
burners using DSI.
5 . Pilot turndown test, all installations using a pilot.
6 . Hot refractory hold-in test, all installations.
7 . Ignition interference test, all installations using flame rods.
8 . Flame signal with hot combustion chamber, all installa-
tions.
9 . Safety shutdown tests, all installations.
See Fig. 14 for location of component parts and see Fig. 5
or 6 or Q7800 Specifications, form 65-0084, for terminal
locations.
Preliminary Inspection
When performing the following inspections, check to verify:
1 . Wiring connections are correct and all terminal screws are
tight.
2 . Flame detector is clean, installed and positioned properly.
(Check the applicable installation instructions.)
3 . Correct combination of amplifier and flame detector is
used. See Table 4.
4 . Plug-in amplifier is securely in place.
5 . Burner is completely installed and ready to fire. (Consult
equipment manufacturer instructions.)
6 . Fuel lines are purged of air.
7 . Combustion chamber and flues are clear of fuel and fuel
vapors.
8 . Power is connected to the system disconnect switch (mas-
ter switch).
9 . Lockout switch is reset (push in reset pushbutton) only if
the relay module is powered; see Fig. 14.
10 . System is in the STANDBY condition and POWER LED is
energized.
11 . All limits and interlocks are reset.
Flame Signal Measurement
Measure the flame signal at the appropriate times defined in
the following checkout tests. Read the flame signal volts dc at
the flame amplifier test jacks + and - (Com). See Fig. 17 and
Table 13.
Table 13. Flame Signal.
a
Maximum Expected dc Voltage
5.0 Vdc at the KDM
or
5.0 Vdc at a one megohm per volt meter.
20

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rm7890Rm7895Rm7890bRm7895a

Table of Contents