venting installation
EN

4.3.4 horizontal air terminal installation

WARNING
!
Risk of fire! Do not allow loose materials or insulation to touch the vent pipe. Remove insulation to allow for the
installation of the attic shield and to maintain clearances to combustibles.
Move the appliance into position. Measure
A.
the vent length required between terminal and
appliance taking into account the additional
length needed for the fi nished wall surface and
any 2" (50.8mm) overlaps between venting
components.
B.
Apply a heavy bead of Mill Pac sealant
(W573-0007) (not supplied) to the outer edge of
the inner collar of the appliance. Attach the fi rst
inner rigid pipe component and secure using a
minimum of three screws. Repeat using the outer
rigid pipe. Seal using Red RTV Silicone (W573-0002)
(not supplied).
Insert the vent pipes through the fi restop maintaining the required clearance to
C.
combustibles. Apply a heavy bead of Red RTV Silicone (W573-0002) (not supplied) to both the
inner sleeve and outer sleeve of the air terminal. Slide the terminal sleeves into the rigid pipes a minimum
of 1 1/4". Holding the air terminal (lettering in an upright, readable position), secure to the exterior wall and
make weather tight by sealing with caulking (not supplied).
The air terminal mounting plate may be recessed into the exterior wall or siding no greater than the
depth of the return fl ange.
note:
When installing terminals above a roof line or against a wall, avoid areas that allow excess water to fall directly on
the terminals (i.e. eaves troughs).
36
W415-2370 / D / 12.09.20
#10x2"
SCREWS
CAULKING
OUTER
RIGID
PIPE
2" (50.8mm) OVERLAP
INNER
RIGID
PIPE
HI-TEMP
SEALANT
18.3A

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ascent 46 b46ntreAscent 46 b46ptrAscent 46 b46ptre

Table of Contents