Installation - PROMIENNIKI GAZOWE SBC 2 Operating And Maintenance Manual

Ceramic radiant heaters
Table of Contents

Advertisement

CERAMIC RADIANT HEATERS

Installation

During first start it is important to make preliminary reviews what guarantee proper functioning of
devices. It is necessary to do activities mentioned below:
1. Check if gas installation is air tights and if diameters are proper.
2. Check if gas pressure is the same as it is written on rating plate
3. Check if gas valve is properly connected with radiator.
4. Check if polarity of system F/N is marked on connection and if there is ground
5. Check if support and chain are strongly installed and a bolts are screwed down
Radiator can be installed on walls, pillars by arms screwed down to heaters construction in prepared
place with screwed holes under M 8 bolts, or by a chain to a cailing using supports type "S".
pic. 3
ATTENTION: it is strictly forbidden to supply the gas circuit with pressure exceeding 60
mbar. This may damage the valve.
EN.SBC_v2_1 Feb 2019
Promienniki Gazowe
pic. 4
.
Sp. z o.o
9