9.2
Use of the 40 kVA distributor
To make full use of 40 kVA, both a 40 kVA and a 20 kVA installation distributor is required. The 40 kVA
is fully available due to forwarding and symmetrical load distribution to both installation distribu-
tors.
The two installation distributors can thus be operated as follows:
• spatially separated, e.g. on an exhibition stand with 40 kVA
• for supplying e.g. two exhibition stands with 20 kVA each
The 40 kVA installation distributor can also be operated stand-alone with a corresponding adapter
on a 20 kVA connection. In this case max. 20 kVA is available
9.3
Measuring device
If your installation distributor has a measuring device, it must be put into operation. Please read the
operating instructions of the manufacturer's measuring device.
The recommissioning (e.g. resetting RCD) can be carried out by trained laypersons.