1. 60Hz
u Example Connection of Transmission Cable
1 Outside Unit
3 Phase 3 Wires
Power supply
60Hz 220V
(Main Switch)
Power supply switch
(Switch)
Power supply
1 Phase 60Hz
220V
WARNING
• Indoor Unit ground Lines are required for preventing electrical shock accident during current leakage,
Transmission disorder by noise effect and motor current leakage (without connection to pipe).
• Don't install an individual switch or electrical outlet to disconnect each of indoor unit separately from
the power supply.
• Install the main switch that can interrupt all the power sources in an integrated manner because this
system consists of the equipment utilizing the multiple power sources.
• If there exists the possibility of reversed phase, lose phase, momentary blackout or the power goes on
and off while the product is operating, attach a reversed phase protection circuit locally.
Running the product in reversed phase may break the compressor and other parts.
Between Indoor and Master Outside unit
SODU
IDU
INTERNET
B
A
B
The GND terminal is a '–' terminal for the central controller, not Ground Line
52
Outside Unit
Power supply switch
(Switch fuse : ELCB)
DRY1 DRY2 GND
12V
A
3
3 Phase 3 Wires Power line(R, S, T)
Transmission line (3 line): Wired remote control
Single Phase of power supply line(L, N)
Transmission line (2 shield line): Between Indoor Unit and Outside Unit
Master
Outside unit
4
3
4
Pull Box(Installer option)
3
4