30HZ/HZV 043-280
Water-Cooled/Condenserless
Liquid Chillers
Nominal cooling capacity 30HZ: 134-783 kW
Nominal cooling capacity 30HZV: 126-735 kW
50 Hz
Installation, operation and maintenance instructions

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Pro-Dialog Plus 30HZ and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Carrier Pro-Dialog Plus 30HZ

  • Page 1 30HZ/HZV 043-280 Water-Cooled/Condenserless Liquid Chillers Nominal cooling capacity 30HZ: 134-783 kW Nominal cooling capacity 30HZV: 126-735 kW 50 Hz Installation, operation and maintenance instructions...
  • Page 2: Table Of Contents

    Contents 1 - IntRoDUCtIon ..................................4 1.1 - Installation safety considerations ............................4 1.2 - Equipment and components under pressure ........................4 1.3 - Maintenance safety considerations ............................4 1.4 - Repair safety considerations ..............................5 2 - PRelImInaRy CheCks ..............................6 2.1 - Check equipment received ..............................
  • Page 3 8 - maIn oPtIons anD aCCessoRIes ..........................24 8.1 - Units for low evaporator outlet temperature applications (options 5 and 6) ..............24 8.2 - Electrical protection to IP44 (option 20)..........................24 8.3 - High- and low-pressure gauges (option 26) ........................24 8.4 - Compressor oil pressure safety device ..........................
  • Page 4: Introduction

    These products incorporate equipment or components under tightness check and verify with the manufacturer that the pressure, manufactured by Carrier or other manufacturers. circuit integrity has not been impaired. If damage is detected We recommend that you consult your appropriate national...
  • Page 5: Repair Safety Considerations

    NOTE: The unit must never be left shut down with the • At least once a year thoroughly inspect the protection liquid line valve closed, as liquid refrigerant can be trapped devices (valves). If the machine operates in a corrosive between this valve and the expansion device.
  • Page 6: Preliminary Checks

    Never apply an open flame or live steam to a refrigerant Close the entering and leaving water shutoff valves and container. Dangerous overpressure can result. If it is purge the unit hydronic circuit, before working on the necessary to heat refrigerant, use only warm water. components installed on the circuit (screen filter, pump, water flow switch, etc.).
  • Page 7: Moving And Siting The Unit

    2.2 - Moving and siting the unit • Verify that all safety and environmental protection devices and arrangements are in place and comply 2.2.1 - moving with the current European standard. • Verify that all document for pressure containers, cer- See chapter 1.1 “Installation safety considerations”.
  • Page 8: Dimensions, Clearances

    3 - DIMENsIONs, ClEaRaNCEs 3.1 - 30hZ/hZV 043-065 3.2 - 30hZ/hZV 091-225 2550...
  • Page 9: 30Hz/Hzv 250-280

    3.3 - 30hZ/hZV 250-280 legend 30hZ - units with condenser 2452 1520 Evaporator 2750 1505 2750 1505 Condensers 2630 1915 2940 1915 Clearances required for operation and maintenance 2940 1915 Clearances recommended for heat exchanger tube removal 2940 1915 3550 1915 Power supply 3550...
  • Page 10: Physical And Electrical Data For 30Hz/Hzv

    4 - PhysICal aND ElECTRICal DaTa FOR 30hZ/hZV 4.1 - Physical data 30hZ/hZV Net nominal cooling capacity* 30HZ 30HZV Operating weight** 30HZ 1090 1183 1252 2039 2370 2460 2510 2730 2830 3505 3805 4470 4900 30HZV 1018 1672 1960 2000 2040 2260 2300...
  • Page 11: Electrical Data

    Power supply frequency variation: ± 2 Hz. accordance with all applicable codes. • The Carrier 30HZ/HZV chillers are designed and built to ensure conformance The neutral (N) conductor must not be connected directly to the unit (if necessary use a transformer).
  • Page 12: Power Supply

    The following is only to be used as a guide- refer to the wiring diagrams. line, and does not make Carrier in any way liable. After wire sizing has been completed, using the certified dimensional WARNINg: Operation of the chiller with an improper...
  • Page 13: Application Data

    °C Notes For minimum chilled water flow rate For application requiring operation at less than 6.8°C, contact Carrier for unit selection using the Carrier electronic catalog. For operation between 4°C and -15°C, the unit must be equipped with option 5 or 6, and the use of anti-freeze is required.
  • Page 14: Variable Flow Evaporator

    5.4 - Variable flow evaporator It is often necessary to add a buffer water tank to the circuit in order to achieve the required volume. The tank must Variable evaporator flow can be used in standard chillers. itself be internally baffled in order to ensure proper mixing The chillers maintain a constant leaving water temperature of the liquid (water or brine).
  • Page 15: Condenser Water Flow Rates

    5.7 - Condenser water flow rates 5.8 - Condenser water flow restrictor 30hZ/hZV Passes Minimum flow rate, l/s* Maximum flow rate, l/s** CAUTION: To ensure correct operation of the units, these Closed loop Open loop restrictors must be installed. The restrictor is supplied with 1.20 3.60 14.80...
  • Page 16: Water Connections

    In case additives or other fluids than those recommend- ed by Carrier are used, ensure that the fluids are not considered as a gas, and that they belong to class 2, as defined in directive 97/23/EC.
  • Page 17: Water Connections

    Tighten in the pairs and instruction will void the Carrier guarantee. sequence indicated according to the size of bolt (see below) using a torque value at the low end of the range given.
  • Page 18: Frost Protection

    6.6 - Refrigerant line connections (30hZV) 6.4.2 - Pipe connections After welding the pipes to the flanges previously removed 6.6.1 - Recommendations for the installation of liquid from the water boxes: chillers with remote condensers Reinstall the pipes and tighten lightly to a torque at To guarantee optimum and reliable performance of the the low end of the range.
  • Page 19 6.6.3 - Use of pipe sizing diagrams 6.6.5 - liquid line sizing On page 23 of this document two pipe sizing diagrams are The 30HZV compressors are supplied with an oil that is shown. They allow an estimate of the cooling capacity, corre- fully miscible with refrigerant R-407C in the liquid phase.
  • Page 20 Table 1 - R-407C correction factors for copper tube 30hZV saturated suction temperature, °C Cond. temp. °C 2.01 1.36 1.09 1.61 1.34 1.07 1.31 1.30 1.06 1.07 1.26 1.04 0.89 1.23 1.03 0.74 1.19 1.01 2.11 1.27 1.08 1.69 1.23 1.06 1.37 1.19...
  • Page 21 Discharge piping legend 1/2” 3/8” 3/4” 7/8” 1-1/8” 1-3/8” 1-5/8” 2-1/8” Cooling capacity (kW) liquid piping legend 3/8” 1/2” 5/8” 3/4” 7/8” 1-1/8” 1-3/8” Cooling capacity (kW)
  • Page 22: Operation Of Two Units In Master/Slave Mode

    NOTE: Use only oils which have been approved for the compressors. Never use oils which have been exposed to air. Recommended oils: • Carrier specification: PP 47 26 • Mobiloil EAL 68 (original charge) 7.3 - Pressure vessels 7.3.1 - Condensers (30hZ units) The condensers (one per circuit) are shell-and-tube conden- sers.
  • Page 23: Electronic Expansion Device (Exv)

    7.4 - Electronic expansion device (EXV) coatings to which they are applied. This is also the case for the products originally supplied by Carrier. These are an option for sizes 30HZ/HZV 043-065. The NOTES: Monitoring during operation, re-qualification,...
  • Page 24: Main Options And Accessories

    8 - MaIN OPTIONs aND aCCEssORIEs 8.7 - additional capacity step 30hZ/hZV 043 to 065 (option 94) Depending on the applications for which the units are selected, they can be equipped with options. This chapter Compressor B1 of the 30HZ 043-065 units is equipped with describes the main components that require special infor- a capacity reduction that increases the available capacity mation for correct start-up and maintenance of these units,...
  • Page 25: Maintenance

    9 - MaINTENaNCE 9.2 - Maintenance of the refrigerant circuit During the unit operating life the service checks and tests • Keep the unit itself and the space around it clean and must be carried out in accordance with applicable national free of obstructions.
  • Page 26: Electrical Maintenance

    apparent and actual subcooling Leak detection is especially important for units charged with refrigerant R-407C. Depending on whether the leak R-407C occurs in the liquid or in the vapour phase, the proportion of the different components in the remaining liquid is not the same.
  • Page 27: Evaporator Maintenance

    • the insulating foam is intact and securely in place. be replaced. Check with Carrier the effect upon chiller per- • the sensors are correctly operating, secured and formance of plugging a number of tubes. Carrier will need positioned.
  • Page 28: Corrosion Control

    When rebuilding the cooler, new gaskets must always be by a coating of powder or liquid paint. To prevent the risk used. They must conform to the Carrier specification for of blistering corrosion that can appear when moisture compressed gaskets.
  • Page 29: Start-Up Checklist For 30Hz/Hzv Liquid Chillers (Use For Job File)

    10 - sTaRT-UP ChECklIsT FOR 30hZ/hZV lIqUID ChIllERs (UsE FOR jOB FIlE) Preliminary information Job name: ....................................... Location: ........................................ Installing contractor:..................................... Distributor: ......................................Start-up preformed by: ..................................equipment Model No..................Serial No..................Compressors Circuit a Circuit b 1. Model No.................. 1. Model No................Serial No.
  • Page 30 Unit start-up CWP starter has been properly interlocked with the chiller Oil heaters have been energized for at least 24 hours Oil level is correct All discharge, suction and liquid valves are open Unit has been leak checked (including fittings) Locate, repair, and report any refrigerant leaks ..........................................
  • Page 31 Perform test function (indicate positive result): WARNINg: Once power is supplied to the unit, check the display for any alarms, such as phase reversal. follow the TEST function instructions in the Controls and Troubleshooting literature (follow the procedure in the Controls IOM). Be sure all service valves are open before beginning the compressor test section.
  • Page 32 Order No.: 13412-76, 12.2008 - Supersedes order No.: 13412-76, 03.2003. Manufactured by: Carrier SCS, Montluel, France Manufacturer reserves the right to change any product specifications without notice. Printed in the Netherlands...