4.4 – Commissioning of the HON Cocon
Start at 4.3.2.1(first time only)
1
Check if regulator & line pressures are set to the approximate set points. The
regulator should be preset slightly below the grid pressure.
2
Crack upstream & downstream block valves in the following order.
3
Gradually open the downstream isolation valve of the HON Cocon. A short
pressure peak could occur at this point. To avoid triggering of the slam shut
valve, depress and hold the reset button at this point until fully open.
4
Gradually open downstream block valve.
5
Gradually open upstream isolation valve of the HON Cocon.
6
Gradually open the upstream block valve.
7
Increase the regulator pilot spring tension by adjusting the screw inwards until the required set point is
reached in the outlet piping.
8
Fine tune the regulator if necessary.
Notes:
Change pressure spring of pilot for next higher in range to increase damping if necessary.
Install a flow restrictor in the motorization line of the pilot to increase damping further if required. (Check with
manufacturer for advise)
To take the unit out of operation, close the upstream block valve first
Do not forget to connect all data‐transmitting devices
Clean and grease the seal/sealings surfaces before mounting the covers.
Operators manual underground gas pressure reducing station
Operators manual
© 2017 Honeywell International Inc.
Type: HON COCON 13
Page 25