4.4 – Commissioning of the HON Cocon 
 
 
Start at 4.3.2.1(first time only) 
 
 
1
Check if regulator & line pressures are set to the approximate set points. The  
 
regulator should be preset slightly below the grid pressure. 
 
2
Crack upstream & downstream block valves in the following order. 
 
 
3
Gradually open the downstream isolation valve of the HON Cocon. A short  
  pressure peak could occur at this point. To avoid triggering of the slam shut  
  valve, depress and hold the reset button at this point until fully open. 
 
 
Gradually open downstream block valve. 
 
 
Gradually open upstream isolation valve of the HON Cocon. 
 
 
Gradually open the upstream block valve. 
 
 
Increase the regulator pilot spring tension by adjusting the screw inwards until the required set point is 
reached in the outlet piping. 
 
 
Fine tune the regulator if necessary. 
 
Notes: 
 
 
 Change pressure spring of pilot for next higher in range to increase damping if necessary. 
 Install a flow restrictor in the motorization line of the pilot to increase damping further if required. (Check with 
manufacturer for advise) 
 To take the unit out of operation, close the upstream block valve first 
 Do not forget to connect all data‐transmitting devices 
 Clean and grease the seal/sealings surfaces before mounting the covers. 
 
 
 
 
Operators manual underground gas pressure reducing station
Operators manual
 
© 2017 Honeywell International Inc.
Type: HON COCON 13
 
Page 25

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents