Electrical Installation
Apply Power and Verify Operation
Apply Power and Verify Operation
1. Apply –48 VDC power to Access Navigator and verify the following front panel status indications
(see Figure 6-26).
Requirement:
Requirement:
2. If second (redundant) controller is present, verify the following front panel status indications.
Requirement:
Requirement:
NOTE:
Connections on
Power
Active
Controller
Controller 'A' Indicators
6-40
CONTROLLER A POWER indicator lights green.
CONTROLLER A ACTIVE indicator lights green.
CONTROLLER B POWER indicator lights green.
CONTROLLER B ACTIVE indicator is off.
If power indicators do not light, check power connections (see DC Power
page
6-35).
Figure 6-26. Location of Front Panel Power-On Status LEDs
Controller 'B' Indicators
August 2003
Access Navigator - Release 1.8