COMMISSIONING MANUAL QT/QST553 Water Heater Control Unit CS20 Chiller Carbonator BOILIN G CHILLED SPARKLING BOILIN G CHILLED SPARKLING HOT & COLD 110V/60Hz...
Page 2
1. The H20 (left side of the water heater) is connected to the WATER IN on the chiller. • QUATREAU COLLECTION BEFORE YOU START CHILLER WATER HEATER • SECTION A: COMMISSIONING SEQUENCE...
Page 3
Repeat every minute for 5 min- show on the top right of the water heater. Commissioning sequence for utes. Quatreau Touch™ and SmartTap™ 4. When the green light on the water heater Boilers (553-B) unit appears and the red light goes out, the water heater has reached its temperature.
Page 4
2. Turn off the mains cold water feed to the so that the pump can continue to feed pres- 5. Now re-open the mains cold water supply Repeat this process for two (2) more water heater Inlet. surized water into the chamber where it mix- to the water heater Inlet.